The Trojan Large Component Removal Project

机译:特洛伊木马大型组件拆除项目

获取原文

摘要

On November 1, 1995, Portland General Electric (PGE) Company completed the Large Component Removal (LCR) Project, which represented the first phase of decommissioning the Trojan Nuclear Plant. This project entailed removing the four steam generators and pressurizer from the Containment Building, preparing them as their own shipping containers, and transporting them via barge and overland transporter to the U.S. Ecology low-level radioactive waste facility on the Hanford Reservation near Richland, Washington. The project had been in the planning stage since the plant was permanently closed on January 4, 1993. Even greater regulatory oversight than normal at a nuclear facility was involved because 1) the project was performed prior to the Decommissioning Plan being approved by the Nuclear Regulatory Commission (NRC), 2) the existing regulations did not apply directly to the shipments, and 3) water and land transport were involved. Finally, court actions in response to cases brought by Trojan as well as Yankee Rowe opponents had to be dealt with during implementation of the project.
机译:1995年11月1日,波特兰通用电气(PGE)公司完成了大量的拆除(LCR)项目,该项目代表了木马核电站退役的第一阶段。该项目需要从容器建筑中拆下四个蒸汽发生器和加压器,准备它们作为自己的运输集装箱,并通过驳船和陆上运输商将其运送到华盛顿里奇兰附近的Hanford预订的美国生态低水平的放射性废物。该项目一直在规划阶段,自1993年1月4日植物永久关闭。甚至更大的监管监督甚至涉及核设施正常的监管,因为1)该项目是在核监管批准的退役计划之前进行的2)委员会(NRC),2)现行法规没有直接申请出货量,3)水和陆地运输涉及。最后,法院行动为响应特洛伊木马而带来的案件以及在项目实施期间必须处理扬基罗对手的案件。

著录项

相似文献

  • 外文文献
  • 中文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号