The Eglinton Crosstown Light Rail Transit (ECLRT) Project involved the construction of 11 km of 6.3m excavated diameter twin tunnels beneath Eglinton Avenue in Toronto, in advance of shored excavations for future cut-and-cover station construction. Over 37,000 cubic meters of dense glacial and interglacial soils were improved by the jet grouting methods to depths of up to 43 meters below ground surface (mbgs). Jet grouting was performed at station headwalls and tunnel cross-passages to manage groundwater and improve soil stability. The paper discusses the implementation of the jet grouting work in a congested urban environment, the quality control methodology and the effectiveness of the jet grout blocks during tunneling.
机译:Eglinton Crosstown轻轨交通(ECLRT)项目涉及在多伦多的Eglinton Avenue下方建造11公里,直径6.3m的双直径隧道,在岸上开挖之前为将来的明挖掩盖车站建设做准备。通过喷射灌浆方法将超过37,000立方米的致密冰川和间冰质土壤改良到了地下43米以下的深度。在车站端墙和隧道交叉通道进行喷射注浆,以管理地下水并提高土壤稳定性。本文讨论了在拥挤的城市环境中喷射注浆工作的实施情况,质量控制方法以及隧道施工中喷射注浆砌块的有效性。

著录项

相似文献

  • 外文文献
  • 中文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号