Comparison Between Calculated and Actual Face Pressures in EPB TBMs-Case Studies in Seattle, WA

机译:EPB TBM中计算的和实际的面压力之间的比较-华盛顿州西雅图的案例研究

获取原文

摘要

Tunnel face instability is one of the most common issues in EPB tunneling. The evaluation of an ideal face support pressure is a critical element in the design and construction phases of EPB tunneling. In this study, measured tunnel face pressures in three EPB tunneling projects (University Link U230 and U220 projects and the Northgate Link Extension N125 Project) for Sound Transit in Seattle, WA are compared with the calculated analytical methods. This comparison shows that the analytical methods generally overestimate the required tunnel face support. The best practice for managing the face pressure in EPB tunneling operation is discussed based on the experience gained through these projects. Furthermore, the algorithm that is developed for identifying ground loss in these projects is addressed.
机译:隧道工作面不稳定性是EPB隧道技术中最常见的问题之一。在EPB隧道的设计和施工阶段,理想的面部支撑压力的评估是至关重要的元素。在这项研究中,将华盛顿州西雅图市的三座EPB隧道工程(University Link U230和U220工程以及Northgate Link Extension N125工程)中测得的隧道工作面压力与计算的分析方法进行了比较。这种比较表明,分析方法通常会高估所需的隧道工作面支撑。根据从这些项目中获得的经验,讨论了在EPB隧道作业中管理工作面压力的最佳做法。此外,解决了为识别这些项目中的地面损失而开发的算法。

著录项

相似文献

  • 外文文献
  • 中文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号