Technical Approach to Lining Design for Internal Pressure and Fault Offsets on the JWPCP Effluent Outfall Tunnel
The Sanitation Districts of Los Angeles County is planning to construct a new, approximately 7-mile-long (11.3 km) effluent outfall tunnel to be excavated by TBM and lined with precast concrete segments. Anticipated net operating pressures within the tunnel are expected to approach 3 bar. To counteract joint opening and exfiltration leakage, an approach has been investigated to post-tension the precast concrete tunnel lining with steel tendons. The tunnel alignment crosses several seismically active fault zones, at which installation of steel pipe is proposed as a secondary inner lining to mitigate potential offset displacements. This paper discusses the tunnel lining design approach and methods used to address these unique challenges.