Internal Forces Arising in the Segmental Lining of an Earth Pressure Balance-Bored Tunnel

机译:土压力平衡钻孔隧道分段衬砌中产生的内力

获取原文
获取原文并翻译 | 示例
           

摘要

This paper presents experimental data obtained by long-term monitoring of the strains occurring in several segments of a precast RC segmental lining adopted to support a bored tunnel. Careful and tight control of the strains was also carried out during the early installation stages, which only lasted a few hours. The strains were measured using vibrating wire gauges embedded in the segments during construction at the manufacturer's plant. The measurements were recorded using a wireless data logger, which allowed accurate follow up of the strain changes in the segments beginning with the concreting stage and for a long time after the tunnel construction. With reference to the various construction stages, the measured strains are presented and discussed. Their maximum values are just a few hundred microstrains, making the thermal effects on the gauge readings significant. For this reason the problem of their elimination is briefly addressed in the paper. The process used to derive the internal forces in the lining is not at all straightforward and the paper describes the process and reports the obtained internal forces both in short- and long-term conditions.
机译:本文介绍了通过长期监测用于支撑钻孔隧道的预制RC分段衬砌几段中发生的应变而获得的实验数据。在安装的早期阶段也进行了仔细而严格的控制,仅持续了几个小时。在制造商的工厂进行建造期间,使用嵌入在节段中的振动线规对应变进行了测量。使用无线数据记录仪记录测量结果,该记录仪可以准确跟踪后续段的应变变化(从混凝土阶段开始),并在隧道施工后的很长一段时间内。参照各个施工阶段,介绍并讨论了所测得的应变。它们的最大值仅为几百个微应变,从而使热量对仪表读数的影响显着。因此,本文中简要介绍了消除它们的问题。得出衬里内力的过程一点也不简单,本文描述了该过程并报告了短期和长期条件下获得的内力。

著录项

相似文献

  • 外文文献
  • 中文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号