Cooper Interceptor - 54' Gravity Sewer Rehabilitation by Cured-in-Place Pipe (CIPP) Methodology for North Charleston Sewer District

机译:库珀拦截器-北查尔斯顿下水道地区的现浇管道(CIPP)方法对54'重力下水道进行修复

获取原文

摘要

The rehabilitation project illustrated project management and coordination with the community and stakeholders can be more challenging than the technical design. The largest technical aspect of this large-bore sewer rehabilitation was design of the bypass. Another lesson learned was that large bureaucratic departments such as the SCDOT can respond favorably to open and direct communications. As engineers, we often focus too heavily on our role and on the technical aspects of projects. This endeavor would not have been successful, or even possible, without the effort toward teambuilding and buy in from the community. Consider the different organizations playing major roles in addition to the Owner, Engineer and Contractor, which included: Norfolk-Southern Railroad, SCDOT and their utility coordination consultant, the City of North Charleston, the Charleston County School Board, the SC Department of Health and Environmental Control, commercial business property owners and local residents. During the development and execution of the project plan, there were times when it was necessary for the project managers to relinquish control, a difficult proposition for many Engineers, and allow these contributing roles to be fulfilled. Public relations and community acceptance require effort and are critical to project success. Lastly, the repair of underground infrastructure before the situation becomes critical is the opportunity to turn a liability into an asset.
机译:修复项目说明了项目管理以及与社区和利益相关者的协调可能比技术设计更具挑战性。这种大口径下水道修复的最大技术方面是旁路的设计。另一个经验教训是,诸如SCDOT之类的大型官僚部门可以对公开和直接的沟通做出积极反应。作为工程师,我们经常过于专注于我们的角色和项目的技术方面。如果没有团队建设和社区参与的努力,这种努力就不会成功,甚至不可能。除所有者,工程师和承包商外,还考虑不同的组织,其中包括:诺福克南部铁路,SCDOT及其公用事业协调顾问,北查尔斯顿市,查尔斯顿县学校委员会,南卡罗来纳州卫生部和环境控制,商业财产所有人和当地居民。在项目计划的开发和执行过程中,有时项目经理有必要放弃控制权,这对许多工程师来说都是一个艰巨的命题,并使这些贡献性角色得以实现。公共关系和社区的接受度需要付出努力,对于项目的成功至关重要。最后,在情况变得严重之前修复地下基础设施是将债务转化为资产的机会。

著录项

相似文献

  • 外文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号