Optimal path planning for material and products transfer in steel works using ACO

机译:使用ACO的钢厂材料和产品转移的最佳路径规划

获取原文

摘要

In steel works, steel production from raw material to final product includes several processes. In the processes, pit iron from blast furnace is transported from furnace to storing yards going through factories. For the transportation, because of weight and high temperature of pit iron, torpedo cars towed by a locomotive on a railway in the compounds are used. For effective production, optimal scheduling of transportation is necessary. The transportation includes many constraints; there exist several factories where they should step by, an order among the factories to step by, restricted transportation time, and minimum working time in factories. Hence, to plan the schedule requires complicated calculation and computation time. Also, when an accident occurs and some paths in the plan are closed, they need calculate a new detour in short time period.
机译:在钢铁厂中,从原材料到最终产品的钢铁生产包括几个过程。在此过程中,高炉的铁水从高炉运到经过工厂的堆场。为了运输,由于矿井铁的重量和高温,在复合物中使用了由机车在铁路上拖曳的鱼雷车。为了有效地进行生产,必须对运输进行最佳调度。运输有很多限制;有几家工厂应该步行,工厂之间要下令停车,运输时间受到限制,并且工厂的工作时间最短。因此,计划时间表需要复杂的计算和计算时间。另外,当发生事故并且计划中的某些路径被关闭时,他们需要在短时间内计算出新的de回路径。

著录项

相似文献

  • 外文文献
  • 中文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号