April's Fury: Alabama Power's Transmission Organization Battles Historic Losses after April 27th Storms

机译:四月的愤怒:阿拉巴马州电力的传输组织在4月27日风暴后战斗历史损失

获取原文

摘要

This paper will assess the impact of the April 27th storms that devastated the Alabama Power service territory. It will assess and scrutinize the storms' characteristics, statistics of losses, failures of materials, and the restoration efforts from the utilities perspective. Before sunrise on April 27,2011, a round of tornados and straight line winds tore through West Central and Northwest Alabama. By 8:20 am, Alabama Power Transmission and Distribution crews were hard at work restoring power to 270,767 customers that were affected by the early morning onslaught. As mid-morning approached, office personnel and upper management became concerned about the ominous forecast coming from the National Weather Service for the afternoon storm systems headed toward Alabama. As early afternoon warnings loomed, all restoration efforts were halted and crews were sent to secure locations to ride out the deteriorating weather. By late afternoon, the true stress test for catastrophic system damage took place as 62 tornados tore through the state of Alabama. By midnight, Alabama Power had 412,229 customers in the dark, 171 transmission lines out, 438 transmission structures down or damaged, 318 substations out, 6 substations with major damage, and 2 of those 6 left unrecognizable. The seven days following the storms led to proactive and reactive restoration efforts by the Alabama Power transmission team. The value of this information lies in the opportunity for other utility companies to look inside this storm's devastation and dissect their own disaster plans to become better prepared for Mother Nature's fury.
机译:本文将评估4月27日风暴摧毁阿拉巴马州电力服务领域的影响。它将评估和仔细审查风暴的特征,损失统计,材料的失败以及公用事业视角的恢复努力。在2011年4月27日的日出之前,一轮龙卷风和直线风穿过西部中央和西北阿拉巴马州。上午8:20,阿拉巴马州的电力传播和分销人员在工作恢复功率为270,767名受到清早冲击的顾客的愿望。正如中午接近的,办公室人员和高层管理人员对来自朝向阿拉巴马州的下午风暴系统的国家天气服务的不祥预测变得担忧。随着早期警告的临近,所有恢复努力都被停止,船员被送到保护地点以乘坐恶化的天气。下午晚些时候,灾难性系统损害的真正压力测试发生在62个龙卷风撕裂,通过阿拉巴马州。到了午夜,阿拉巴马电力有412229个用户在黑暗中,171条传输线出来,438层传输结构向下或损坏,318个变电站出来,6个站有重大损害,而那些6人无法辨认的2。暴风雨之后的七天导致阿拉巴马州电力传输团队积极主动和反应恢复努力。这些信息的价值在于其他公用事业公司在这场风暴的毁灭中展示了其他公用事业公司的机会,并解剖自己的灾难计划,以更好地为大自然的愤怒做好准备。

著录项

相似文献

  • 外文文献
  • 中文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号