The Saratoga Road Culvert Replacement Project was intended to replace a damaged 18-inch diameter concrete culvert that crosses underneath Saratoga Road on Whidbey Island, Washington. The replacement culvert was originally planned as a 54-inch diameter steel casing with a 48-inch HDPE liner. The proposed crossing was roughly 170 feet long, and ranged in depth from approximately 35 to 45 feet below ground surface.Auger bore pipe jacking was recommended by others to install the 54-inch steel casing. However, the contractor elected to install the casing using pipe jacking combined with hand excavation at the pipe face. After roughly 100 linear feet had been installed, soil and groundwater began to flow into the casing, resulting in the formation of a significant sinkhole above the culvert. Following formation of the sinkhole, the casing was subsequently abandoned in place and the project as designed was terminated.Staheli Trenchless Consultants (STC) was contacted to evaluate feasible alternatives to complete the culvert installation which would both address the current site conditions (including the partially installed 54-inch casing) and pose minimal risk to Saratoga Road during construction. After visiting the site and reviewing the existing geotechnical report, STC recommended open-ended pipe ramming as a feasible method for completion of the culvert installation. The new design rams a 30-inch steel casing through 100 feet of the existing 54-inch casing, and through 70 feet of native soils to daylight. This paper describes the project history in light of the multiple installation attempts and details lessons learned throughout the entire process of pipeline installation.
机译:萨拉托加路涵更换项目旨在替换直径超过18英寸的受损混凝土涵洞,该涵洞横穿华盛顿惠德比岛的萨拉托加路下方。替换涵洞最初计划为直径为54英寸的钢制外壳,带有48英寸的HDPE衬里。拟议的过境点长约170英尺,深度在地面以下约35到45英尺之间。 其他人建议使用螺旋钻顶管安装54英寸钢制套管。但是,承包商选择通过顶管结合手动开挖在管面上安装套管。在安装了大约100线性英尺后,土壤和地下水开始流入套管,导致在涵洞上方形成大量的下沉孔。形成下水道之后,套管随后被弃置就位,并按计划终止了该项目。 与Staheli Trenchless顾问(STC)进行了联系,以评估可行的替代方案来完成涵洞的安装,这既可以解决当前的现场条件(包括部分安装的54英寸套管),又可以在施工期间对Saratoga Road造成最小的风险。在访问了现场并查看了现有的岩土工程报告后,STC建议采用开放式夯管作为完成涵洞安装的可行方法。新设计将一个30英寸的钢制外壳夯入现有54英寸外壳的100英尺,并通过70英尺的天然土壤进行日光照射。本文根据多次安装尝试来描述项目历史,并详细介绍在管道安装整个过程中获得的经验教训。

著录项

相似文献

  • 外文文献
  • 中文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号