首页> 外文会议>2009 rapid excavation and tunneling conference proceedings >TBM TUNNELING AT THE ASHLU HYDROPOWER PROJECT, SQUAMISH, BC
【24h】

TBM TUNNELING AT THE ASHLU HYDROPOWER PROJECT, SQUAMISH, BC

机译:不列颠哥伦比亚省斯夸米什市阿什卢水电站项目的隧道掘进机隧道

获取原文

摘要

The Ashlu Creek Hydro-electric project, located north of Squamish, BC, at the confluence of Ashlu Creek and the Squamish River, comprises a 49 MW run-of-river project and features a 4.08 m diameter, 4.4 km power tunnel and a 128 m deep drop shaft. The Ashlu Creek Hydro-electric project is being developed by Innergex under Ashlu Creek Investments Limited. Site civil works are being completed by Ledcor CMI of Vancouver with tunnel construction by Frontier Kemper Constructors ULC under a lump sum design-build contract. Site works got underway in September 2006 with the construction of the tunnel portal and laydown area. These site works required rock slope stabilization over a 50 m rock slope to secure the laydown area as well as the construction of a tail track muck tipping station and structural wall to facilitate TBM excavation and spoil removal. Starter tunnel construction commenced in early 2007 and TBM tunneling started in the late spring of 2007 and is planned to continue until early 2009. The power tunnel is being excavated using a 1,200 kW Wirth open-type hard rock TBM dressed with 31-17" cutters. The TBM featured two fixed mounted rock bolt drills behind the finger shield: these were removed and replaced with jacklegs to improve access. A probe drill at the end of the main beam is also present. The geology along the 4.4 km power tunnel comprises very strong and generally massive granitic bedrock with rock strength greater than 225 MPa. A unique feature of the project is that no subsurface investigations have been completed for the tunnel however extensive bedrock outcrops are present along the Ashlu Creek valley. A historical quarry exists approximately mid-way along the tunnel alignment that has exposed good quality granitic bedrock. TBM tunneling to date has achieved advance rates of 10-20 m/day with a maximum of 23 m and has encountered all of the anticipated six major fault zones where the installation of various standard high capacity tunnel support was successful to facilitate TBM advance through these sections.
机译:位于不列颠哥伦比亚省Squamish以北,Ashlu Creek和Squamish River交汇处的Ashlu Creek水力发电项目包括一个49 MW的过流项目,其特点是直径4.08 m,电力隧道4.4 km和128米深的下降轴。 Innlux旗下的Ashlu Creek投资有限公司正在开发Ashlu Creek水力发电项目。温哥华的Ledcor CMI将按照一笔总价的设计建造合同,完成温哥华的Ledcor CMI的现场土建工程和Frontier Kemper建造商ULC的隧道建设。随着隧道入口和铺设区域的建设,现场工作于2006年9月开始。这些现场工作要求在50 m的岩质斜坡上稳定岩质斜坡,以确保放下区域,并建造尾轨渣土倾卸站和结构墙,以利于TBM开挖和清除泥土。起动器隧道的建设始于2007年初,TBM隧道的建设始于2007年春末,并计划一直持续到2009年初。电力隧道正在使用配有31-17英寸切割机的1200 kW Wirth敞开式硬岩TBM进行开挖。 。TBM在手指防护罩后面有两个固定安装的锚杆钻头:取下并用千斤顶代替,以改善通行性;在主梁末端也有探查钻头; 4.4 km动力隧道沿线的地质非常岩石强度大于225 MPa的坚硬且通常呈块状的花岗岩基岩项目。该项目的独特之处在于,尚未完成隧道的地下勘测,但沿Ashlu Creek谷地存在大量基岩露头。沿隧道路线一直暴露出优质的花岗岩基岩迄今为止,TBM隧道掘进速度已达到10-20 m /天,最高可达23 m并遇到了所有预期的六个主要断层带,在这些断层带成功安装了各种标准的大容量隧道支护,从而促进了TBM穿越这些断层。

著录项

相似文献

  • 外文文献
  • 中文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号