MONITORING AND ASSESSMENT OF A FRAME TUNNEL BRIDGE DURING JACKING CONSTRUCTION STAGE

机译:顶进施工阶段框架隧道桥的监测与评估。

获取原文

摘要

Jacking is the popular construction method of frame tunnel bridges. There are twoproblems should be solved in the jacking process. One is cracking caused by unbalancedjacking force between the both sides along the railway line,especially for slender frametunnel bridge. The other is cracking caused by different settlement,especially for bridge onsoft subsoil. In this paper the monitoring on a frame tunnel bridge (a structure located inTangshan city,Hebei province,China) is discussed. Before field monitoring a 3-D finiteelement model is created using MIDAS software and the mechanical behavior under differentload cases are analyzed. The critical points are identified and the concrete strain andtemperature at critical points are monitored during the jacking stage. The construction qualityof this tunnel bridge is guaranteed,and helpful advice is proposed for the design,constructionand prevention of cracks of the frame tunnel bridge.
机译:顶进是框架隧道桥梁的流行施工方法。顶升过程中应解决两个问题。一种是由铁路沿线两侧之间的不平衡顶升力引起的开裂,尤其是对于细长的框架隧道桥而言。另一个是由不同沉降引起的裂缝,尤其是桥梁在软土地基上。本文讨论了对框架隧道桥梁(位于中国河北省唐山市的建筑物)的监测。在现场监测之前,使用MIDAS软件创建了3-D有限元模型,并分析了不同载荷情况下的力学行为。在顶升阶段,确定临界点并监控临界点处的混凝土应变和温度。保证了该隧道桥梁的施工质量,并为框架隧道桥梁的裂缝的设计,施工和预防提出了有益的建议。

著录项

相似文献

  • 外文文献
  • 中文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号