Time-cost tradeoff in fuzzy critical path analysis based on (1 − α) × 100 confidence-interval estimates

机译:基于(1-α)×100%置信区间估计的模糊关键路径分析中的时间成本权衡

获取原文

摘要

Project crashing is a method for shortening the project schedule by reducing the time of one or more critical activities to less than its normal activity time. The objective of crashing is to reduce project duration while minimizing the cost of crashing, which is also known as time-cost tradeoff problem. The unknown or vagueness about the time duration for activities has led to the development of fuzzy critical path method and fuzzy time-cost tradeoff problem. In this paper, we introduce a fuzzy approach based on statistical confidence-interval estimates and a distance ranking method for (1 − α) fuzzy number levels. The primary result obtained from this study is a Theorem based on statistical confidence-interval estimates through which the fuzzy critical path and fuzzy time-cost tradeoff problems can be solved efficiently.
机译:项目崩溃是一种通过将一项或多项关键活动的时间减少到少于其正常活动时间的方式来缩短项目进度的方法。崩溃的目的是减少项目工期,同时最大程度地降低崩溃成本,这也称为时间成本权衡问题。关于活动持续时间的未知或模糊性导致了模糊关键路径法和模糊时间成本权衡问题的发展。在本文中,我们介绍了一种基于统计置信区间估计的模糊方法和一种针对(1-α)模糊数水平的距离排序方法。从这项研究中获得的主要结果是基于统计置信区间估计的定理,通过该定理可以有效地解决模糊关键路径和模糊时间成本权衡问题。

著录项

相似文献

  • 外文文献
  • 中文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号