Careful Monitoring Keeps Tunnel on Track—Microtunnel Installation in Flowing Sands Beneath Critical Structures

机译:仔细的监控使隧道保持正常运行—在关键结构下方的流动沙中安装微隧道

获取原文
获取原文并翻译 | 示例

摘要

To meet increasing demand, the City of East Chicago is constructing a new water treatmentrnplant (WTP) designed to treat raw water from Lake Michigan. As part of the overall project a 900-foot gravityrnpipeline was required to convey raw water from an intake structure to the new WTP, which has been successfullyrnconstructed using microtunneling techniques. A 72-inch internal diameter Permalok steel casing was utilizedrnfor installation of the 48-inch internal diameter Hobas carrier pipe. The pipeline was constructed in two separaterntrenchless drives with Drive 2 being the longest and most sensitive. Drive 2 was approximately 760 feet inrnlength and completed through clean, poorly-graded sand below the groundwater table. The drive passed beneathrnseven sets of railroad tracks spanning approximately 140 feet; multiple utility lines that included water, electric,rngas, and telecommunications up to 48 inches in diameter; and approximately 300 feet of Indiana Department ofrnTransportation right-of-way including a highway off-ramp, with associated shallow foundations, and both thernnorth and south bound lanes of Cline Avenue. Due to the propensity for settlement when dealing with runningrnand flowing sands, an extensive geotechnical instrumentation program was conducted during mining. Thisrnpaper will focus on the steps taken by the Owner, Engineer, and Contractor to form effective relationships withrnthe utility and railroad companies to reduce the probability of ground movements, including the use of Drive 1rnto troubleshoot and eliminate issues/problems with means and methods before performing Drive 2.
机译:为了满足不断增长的需求,东芝加哥市正在建造一个新的水处理厂(WTP),用于处理来自密歇根湖的原水。作为整个项目的一部分,需要一条900英尺的重力管道将原水从进水结构输送到新的污水处理厂,该污水处理厂已使用微隧道技术成功构建。内径为72英寸的Permalok钢套管用于安装内径为48英寸的Hobas输送管。管道由两个独立的无槽驱动器构成,其中驱动器2最长且最敏感。驱动器2的长度约为760英尺,并通过地下水位以下的干净,等级不高的沙子完成。驱动器通过了大约140英尺的七套铁轨下面;多条公用设施线,包括直径不超过48英寸的水,电,沼气和电信;印第安纳州交通运输部约300英尺,包括一条高速公路匝道,带有浅层基础,以及克莱恩大道的北行和南行车道。由于在处理流砂和流动砂时易于沉降,因此在采矿期间进行了广泛的岩土工程仪器程序。本白皮书将重点介绍所有者,工程师和承包商采取的与公用事业和铁路公司建立有效关系以减少地面移动的可能性的步骤,包括使用Drive 1rn进行故障排除,并在执行之前消除手段和方法上的问题/问题。驱动器2。

著录项

  • 来源
    《 》|2012年|772-778|共7页
  • 会议地点 Indianapolis IN(US)
  • 作者单位

    Black Veatch Corporation, Gaithersburg, Maryland;

    Black Veatch Corporation, Gaithersburg, Maryland;

    Black Veatch Corporation, Charleston, South Carolina;

    City of East Chicago, East Chicago, Indiana;

  • 会议组织
  • 原文格式 PDF
  • 正文语种 eng
  • 中图分类
  • 关键词

相似文献

  • 外文文献
  • 中文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号