首页> 外文会议>Deep Foundations Institute annual conference on deep foundations >CUT-OFFS IN TEMPORARY COFFER DAMS AS SEEPAGE BARRIERS FOR CONCRETE DAM CONSTRUCTION -A CASE STUDY OF TEESTA -V H E PROJECT IN SIKKIM (INDIA)
【24h】

CUT-OFFS IN TEMPORARY COFFER DAMS AS SEEPAGE BARRIERS FOR CONCRETE DAM CONSTRUCTION -A CASE STUDY OF TEESTA -V H E PROJECT IN SIKKIM (INDIA)

机译:临时混凝土坝作为混凝土坝施工渗水障碍物的切屑-以锡金(印度)TEESTA -V H E项目为例

获取原文

摘要

Cutoff walls are frequently used to slow down or prevent seepage of water through and/or around dams. Cutoff wall is a type of seepage barrier structure designed to reduce the flow of water underneath temporary or main dam. There are number of techniques for the construction of cutoff walls including concrete, Jet grouting and permeation grouting. NHPC LTD, a premier Govt. of India undertaking has been instrumental in the hydro-power development within the country & in nearby countries like Nepal & Bhutan since last four decades. NHPC LTD has completed more than 20 hydro-electric projects with total installed capacity of 6587MW (including capacity addition by JV- NHDC). In all these projects, different types of dams and spillways were constructed in not so benign to extreme challenging geological set up. There has always been challenge associated with the temporary diversion works. The project sites sometimes incur huge river bed excavations in case of concrete gravity dam founded on rock foundation at large depth. The challenges for minimizing the seepage have been well taken care by constructing the dedicated seepage barriers. The construction of cut-off walls have progressed from "conventional continuous trench backfilled with conventional concrete or plastic concrete" to "grout curtain", to "jet grouting" to the "concrete cut-off wall" , the last being the most sophisticated & credible seepage barrier. The efficiency of the cut-off walls are monitored by the seepage quantity observed (reduction of the seepage flow), uplift pressures or exit gradients after construction of cut-off walls. For construction of the main concrete dam, required space is created by the river bed excavation for placing the dam foundation on sound rock. Sometimes there is deep river bed excavation from 30 to 40 m depth or even more as per the available rock profile. Temporary coffer dams are constructed for diverting the river flow through diversion tunnels / channels etc. In deep river bed excavation; there are high chances of the significant seepage through the coffer dam foundation / river bed material due to high hydraulic gradients. Seepage and piping are the main causes of the failure / damage of the temporary coffer dams. If the seepage quantity is too high, then it becomes difficult to handle it by dewatering in the dam pit. Dam concrete is required to be placed unhindered to have a monolithic construction of dam blocks & to have faster construction in the working season. Cut-off walls increase the seepage path considerably thus reducing the exit gradient and further reduction of the seepage thus helping in maintaining the seepage free area for working. As the diversion flood values are increasing due to uncertain storm phenomenon, adverse climatic conditions and to have long working period for faster construction of main dam which is resulting in the substantial increase in the height of temporary coffer dams. The suitability of the proper cut-off barrier needs to be designed in accordance with trial testing and credibility as per the available geological condition. Seepage analysis by FEM software helps to find out the efficacy of the seepage barrier in terms of the flux and exit gradient.
机译:防渗墙通常用于减缓或防止水通过大坝和/或在大坝周围渗漏。防渗墙是一种防渗结构,旨在减少临时或主坝下方的水流。防渗墙的施工技术很多,包括混凝土,喷射灌浆和渗透灌浆。 NHPC LTD,总理。自过去的40年以来,印度的这项事业一直在该国以及尼泊尔和不丹等附近国家的水电开发中发挥了重要作用。 NHPC LTD已经完成了20多个水电项目,总装机容量为6587MW(包括合资公司NHDC的新增装机容量)。在所有这些项目中,建造的不同类型的大坝和溢洪道对极端具有挑战性的地质构造都不是那么有益。临时改道工作一直存在挑战。如果混凝土重力坝建在大深度的岩石基础上,项目工地有时会开挖巨大的河床。通过构建专用的防渗屏障,可以很好地解决使渗漏最小化的挑战。防渗墙的建设已从“用常规混凝土或塑料混凝土回填的传统连续沟槽”发展到“灌浆幕”,再到“喷射灌浆”再发展到“混凝土防渗墙”,最后一道是最复杂的混凝土墙。可靠的防渗屏障。防渗墙的效率通过观察到的渗水量(渗流的减少),防渗墙建造后的抬升压力或出口梯度进行监控。对于主要混凝土坝的建设,河床开挖创造了所需的空间,用于将坝基放置在稳固的岩石上。有时,根据可用的岩石剖面,在30至40 m的深度进行深河床开挖,甚至更多。修建临时围堰水坝,用于通过引水隧洞/渠道等分流河水。由于水力梯度大,很可能会通过围堰基础/河床材料造成大量渗漏。渗水和管道是临时围堰失灵/损坏的主要原因。如果渗漏量太大,则通过在坝坑中脱水将变得难以处理。大坝混凝土要求不受阻碍地放置,以使大块砌块整体成型,并在工作季节内加快施工速度。防渗墙大大增加了渗流路径,从而减小了出口坡度,并进一步减少了渗流,从而有助于维持无渗漏的工作区域。由于不确定的暴风雨现象,不利的气候条件以及漫长的工作周期,导致导流洪水值增加,主水坝的建设速度加快,这导致临时围堰的高度大大增加。根据可用的地质条件,必须根据试验测试和可信度来设计适当的隔断壁垒的适用性。由FEM软件进行的渗流分析有助于根据通量和出口梯度确定渗流屏障的功效。

著录项

相似文献

  • 外文文献
  • 中文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号