首页> 外文会议>Annual Meeting of the AACE International >Modelling Line of Balance Schedules with Start-Finish Relationships
【24h】

Modelling Line of Balance Schedules with Start-Finish Relationships

机译:具有开始-完成关系的余额明细表建模线

获取原文

摘要

The use of the Line of Balance Scheduling Method (LBSM) has been increasing, especially by construction industry companies in Brazil, Finland and Australia. The method addresses to the particularities of construction projects more effectively than the Critical Path Method does. One drawback of the method is the unavailability of commercial software featuring the fundamentals of LBSM. Studies pointed this as a factor that prevents a more frequent use. Recognizing the potential of the method for managing construction projects, the objective of this paper is to propose methodologies for modelling Line of Balance schedules using CPM software. In order to model the schedule, the paper demonstrates the use of the "Start-Finish" logic relationship and its contributions for two different approaches for the modelling: Network and Linear Scheduling Approach. The first approach to demonstrate the design of a CPM network, which simulates the structure and function of a Line of Balance, with the objective of benefiting from CPM calculations. The second approach drops the CPM calculations and focuses on modelling, tuning and balancing individual workflow lines to and from milestones activities.
机译:平衡线调度方法(LBSM)的使用正在增加,尤其是巴西,芬兰和澳大利亚的建筑行业公司。该方法比“关键路径法”更有效地解决了建设项目的特殊性。该方法的一个缺点是无法使用具有LBSM基本原理的商业软件。研究指出,这是阻止更频繁使用的因素。认识到管理项目管理方法的潜力,本文的目的是提出使用CPM软件对“平衡线”进度表进行建模的方法。为了对时间表进行建模,本文演示了“开始-完成”逻辑关系的使用及其对两种不同建模方法的贡献:网络和线性调度方法。演示CPM网络设计的第一种方法,该网络模拟了平衡线的结构和功能,目的是从CPM计算中受益。第二种方法删除了CPM的计算,并着重于对里程碑活动之间的各个工作流程线进行建模,调整和平衡。

著录项

相似文献

  • 外文文献
  • 中文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号