Reviewing Means of Calculating Schedule Updates with Out-of-Sequence Progress

机译:审查计算进度更新的方法

获取原文

摘要

The alternate algorithms of retained logic and progress override were developed tobe utilized on the original ADM (arrow diagramming method) format for CPM. It wasunderstood by initial developers that neither choice was correct but merely set options to beoverly pessimistic or optimistic. Improvements in computers enabling solution of PDM(precedence diagramming method) logic networks implemented only these choices withoutregard to other aspects of the PDM format.A solution avoiding either bias is posited in this paper, and is called by the author a ModifiedOut-of-Sequence Algorithm. While both retained logic and progress override algorithms involveuse of the traditional finish-to-start form of restraint, the modified out-of-sequence algorithmalso utilizes a finish-to-finish form of restraint. The protocol was first suggested by the author in2004 and published in 2005 (and 2010) in CPM in Construction Management, 6th and 7theditions.
机译:保留逻辑和进度覆盖的替代算法已开发为 用于CPM的原始ADM(箭头图示方法)格式。它是 最初的开发人员了解到,两种选择都不正确,而只是将选项设置为 过于悲观或乐观。改进计算机以实现PDM解决方案 (优先级图示方法)逻辑网络仅实现了这些选择,而没有 关于PDM格式的其他方面。 本文提出了一种避免出现任何偏差的解决方案,并且作者称其为“已修改”。 乱序算法。虽然保留逻辑和进度覆盖算法都涉及 使用传统的从头到尾的约束形式,改进的乱序算法 还采用了从头到尾的约束形式。该协议最初是由作者在 2004年,并于2005年(和2010年)在CPM建筑管理中排名第六和第七 版本。

著录项

相似文献

  • 外文文献
  • 中文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号