Nuclear reactors’ construction costs: The role of lead-time, standardization and technological progress

机译:核反应堆的建设成本:交货时间,标准化和技术进步的作用

获取原文

摘要

This paper provides the first comparative analysis of nuclear reactorconstruction costs in France and the United States. Studying the cost ofnuclear power has often been a challenge, owing to the lack of reliabledata sources and heterogeneity between countries, as well as the long timehorizon which requires controlling for input prices and structural changes.We build a simultaneous system of equations for overnight costs andconstruction time (lead-time) to control for endogeneity, using expecteddemand variation as an instrument. We argue that benefits fromnuclear reactor program standardization can arise through short termcoordination gains, when the diversity of nuclear reactors’ technologiesunder construction is low, or through long term benefits from learningspillovers from past reactor construction experience, if those spilloversare limited to similar reactors. We find that overnight construction costsbenefit directly from learning spillovers but that these spillovers are onlysignificant for nuclear models built by the same Architect-Engineer (AE).In addition, we show that the standardization of nuclear reactorsunder construction has an indirect and positive effect on constructioncosts through a reduction in lead-time, the latter being one of the maindrivers of construction costs. Conversely, we also explore the possibility oflearning by searching and find that, contrary to other energy technologies,innovation leads to construction costs increases.
机译:本文提供了核反应堆的第一个比较分析 法国和美国的建筑成本。研究成本 由于缺乏可靠的能源,核电通常是一个挑战 数据来源和国家之间的异质性,以及长期以来 需要控制投入价格和结构变化的视野。 我们为隔夜成本建立了一个同时方程组, 使用预期的时间来控制内生性的构建时间(交货时间) 需求变化作为一种​​手段。我们认为,受益于 核反应堆计划的标准化可能会在短期内出现 核反应堆技术的多样性带来的协调收益 正在建设中的比例较低,或者通过学习可以长期受益 过去反应堆建造经验中的溢出物(如果有的话) 仅限于类似的反应堆。我们发现过夜的建设成本 直接从学习溢出中受益,但是这些溢出仅仅是 对于由同一位建筑师-工程师(AE)建立的核模型具有重要意义。 此外,我们证明了核反应堆的标准化 正在建设中对建设有间接和积极的影响 通过减少交货时间来降低成本,后者是主要的交货时间之一 施工成本的驱动因素。相反,我们也探索了 通过搜索进行学习,发现与其他能源技术相反, 创新导致建筑成本增加。

著录项

相似文献

  • 外文文献
  • 中文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号