A study of the Planned Value Estimation Method for Developing Earned Value Management System in the Nuclear Power Plant Construction Project

机译:核电站建设项目中销售价值管理体系的计划价值估计方法研究

获取原文

摘要

The Earned Value Management System (EVMS) is a project management technique for measuring project performance and progress, and then forward projection through the integrated management and control of cost and schedule. This research reviewed the concept of the EVMS method, and proposes two Planned Value estimation methods for the potential application to succeeding NPP construction projects by using the historical data from the proceeding NPP projects. This paper is to introduce the solution for the problems caused by the absence of relevant management system incorporating schedule and cost, which has arisen as repeated issues in NPP construction project management.
机译:赚取的价值管理系统(EVMS)是一种用于测量项目性能和进度的项目管理技术,然后通过综合管理和控制成本和计划来向前投影。本研究综述了EVMS方法的概念,并提出了两个计划的价值估算方法,以便通过使用Grading NPP项目中的历史数据来接替NPP建设项目。本文是为了介绍缺乏相关管理系统造成的问题造成的问题的解决方案,该计划和成本在NPP建设项目管理中被出现在重复问题。

著录项

相似文献

  • 外文文献
  • 中文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号