CP Data Management Software, Field Computers and Remote Monitoring Facilitate Cathodic Protection System Commissioning

机译:CP数据管理软件,现场计算机和远程监控有助于阴极保护系统的调试

获取原文

摘要

The evaluation, design and commissioning of the expanded cathodic system was one of the final phases in the completion of the 2003 Expansion Project, which nearly doubled the size of a major natural gas transmission pipeline system. The use of laptop-based cathodic protection data management software gave the CP contractor’s crews immediate access in the field to historical data and ad-hoc reports. Rugged handheld field computers with integrated GPS sped up data collection and provided a graphical view of the field data that improved data analysis. Rectifier interruption and monitoring was controlled remotely via the pipeline SCADA network. These technologies as well as cell phones, digital cameras and e-mail were used extensively during the cathodic protection system commissioning to complete the project under a tight time schedule.
机译:扩展阴极系统的评估,设计和调试是2003年扩展项目完成的最后阶段之一,该项目使大型天然气传输管道系统的规模几乎增加了一倍。基于便携式计算机的阴极保护数据管理软件的使用使CP承包商的工作人员可以在现场立即访问历史数据和临时报告。具有集成GPS的坚固耐用的手持式现场计算机加快了数据收集的速度,并提供了现场数据的图形视图,从而改善了数据分析。整流器的中断和监控通过管道SCADA网络进行远程控制。在阴极保护系统调试期间,这些技术以及手机,数码相机和电子邮件被广泛使用,以在紧迫的时间表内完成该项目。

著录项

相似文献

  • 外文文献
  • 中文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号