When the blasting is executed at the face adjacent to existing lining for widening of existing tunnel, serious damage on the existing tunnel lining due to blast will cause less safety during construction. Then, to confirm the safety, the blasting vibration velocity of existing lining was ing was measured at the tunnel con-struction site, and the relationships between the measured data and the site conditions were examined by regression method. As a result, it is made clear that the generated vibration is small and the crack appears in the range of 3 ~ 5 m from the face at most.
机译:当在与现有衬砌相邻的面上进行爆破以拓宽现有隧道时,由于爆破对现有隧道衬砌造成的严重破坏将在施工期间导致安全性降低。然后,为确认安全性,在隧道施工现场对现有衬砌的爆破振动速度进行了测量,并通过回归方法检验了测量数据与现场条件之间的关系。结果,可以清楚地看到,所产生的振动很小,并且裂纹出现在距表面最多3〜5 m的范围内。

著录项

相似文献

  • 外文文献
  • 中文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号