GROUND FREEZING FOR THE EAST SIDE ACCESS NORTHERN BOULEVARD CROSSING- BALANCING SETTLEMENT AND HEAVE CONTROL

机译:地面冻结东侧接入北大道横穿 - 平衡沉降和升降控制

获取原文

摘要

One of the most challenging elements of the MTA Capital Construction Project's East Side Access Project was the Northern Boulevard Crossing which required an SEM tunnel between two 85-ft deep access shafts which extended to as deep as 55 ft below the water table. Tunneling was accomplished beneath a frozen ground arch connecting the two deep excavations, and within very close proximity of the overlying, active subway and elevated transit lines. The work required significant measures to permit installation of freeze pipes and grout pipes through highly variable subsurface conditions below the water table, as well as two critical ground improvement requirements: settlement control and heave control. This paper discusses the pipe installation, the pre-grouting, settlement and heave control, monitoring and instrumentation, and their integration with the overall program.
机译:MTA资本建设项目的东侧接入项目中最具挑战性的元素之一是北部大道交叉路口,在两台85英尺深的深度进入轴之间需要SEM隧道,在水位下方延伸至55英尺深。在冻结的地面拱下面完成了隧道,连接了两个深挖掘,并且在覆盖,有源地铁和升高的传输线的非常接近的附近。该工作要求通过水位下方的高度可变地下条件以及两个关键地面改进要求,允许安装冻管和灌浆管道的措施,以及沉降控制和升降控制。本文讨论了管道安装,预灌浆,结算和升降控制,监控和仪表以及与整体计划的集成。

著录项

相似文献

  • 外文文献
  • 中文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号