In October 2006, a 7m Double Shield TBM, boring through very poor volcanic formations, was pushed back by fluid mud, which presence had not been detected during previous field investigations, due to the high covers characterizing the majority of the tunnel axis. The present work describes the investigations made to gain better knowledge of the conditions in front and all around the TBM, the special measures implemented, the exploratory and bypass tunnels excavated, the extraordinary occurrences came true during the execution of these tunnels, the drainage campaigns, the design of the chamber excavated to free the TBM, the dismounting and restarting of the TBM.
机译:2006年10月,通过液体泥浆向通过非常差的火山形成钻孔7M双屏蔽TBM,由于隧道轴的大部分的高封面,在先前的实地调查期间没有检测到这种存在。本工作描述了为更好地了解前方和TBM周围条件的调查,采取的特殊措施,挖掘出的探索性和旁路隧道,在执行这些隧道的情况下,散布行动活动期间成真,挖掘机的设计挖掘以释放TBM,拆卸TBM的拆卸。

著录项

相似文献

  • 外文文献
  • 中文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号