Determination of 1200 mm working piles deformation parameters, using test of smaller diameter pile for the piled raft foundation of Capital Fort project

机译:首都堡项目桩筏基础小直径桩试验确定1200 mm工作桩变形参数

获取原文
获取原文并翻译 | 示例

摘要

Capital Fort mixed used development comprises a 30-storey, 126 m high office tower and an 8-storey, 35 m high, L-shaped office building, unified with a two storey deep basement. Foundation structure is a raft with a variable thickness under both buildings and bored piles under the high-rise. Deformation and strength characteristics of the soil, received from the geological survey, are used for a preliminary analysis of the combined piled raft foundation. Deformation modules are defined using the results from the standard penetration test. Single pile test is performed for determination of the geotechnical parameters used for refinement of soil analytical model. Working piles are 28 m deep and have a diameter of 1200 mm. Pile with smaller diameter (600 mm) is used for the test. The depth of the tested pile is the same as the working ones. Casing and concrete grade C25/30 are used for the construction of the pile. Anchoring system comprises four working piles. Hydraulic loading system with 8000 kN capacity is used. Measuring system monitors the settlement of the pile head and comprises three dial gauges with 0.01 mm precision, placed at 120 degrees in plan. The pile is loaded in 11 steps of 700 kN each, up to 7700 kN, realizing 30.5 mm settlement. Results from the test and a comparison with the analytical results from the preliminary adopted parameters are presented in the article.
机译:首都堡混合使用的开发项目包括一幢30层,高126 m的办公大楼和一幢三层,高35 m的L形办公楼,并与两层深的地下室统一。地基结构是一栋筏,其在建筑物下均具有可变的厚度,而在高层下则为钻孔桩。从地质调查中获得的土壤变形和强度特性被用于组合桩筏基础的初步分析。变形模块是使用标准渗透测试的结果定义的。进行单桩测试以确定用于完善土壤分析模型的岩土参数。工作桩深28 m,直径1200 mm。测试使用直径较小的桩(600毫米)。被测桩的深度与工作桩的深度相同。套管和C25 / 30级混凝土用于桩的构造。锚固系统包括四个工作桩。使用容量为8000 kN的液压加载系统。测量系统监控桩头的沉降,并包括三个精度为0.01 mm的千分表,它们以平面120度放置。该桩以11个步骤加载,每个步骤700 kN,最大7700 kN,实现30.5 mm的沉降。本文介绍了测试结果以及与初步采用的参数的分析结果的比较。

著录项

相似文献

  • 外文文献
  • 中文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号