首页> 外文会议>International symposium on semiconductor manufacturing >Impact of Tool Installation Delay on Factory Ramp-Up Performance
【24h】

Impact of Tool Installation Delay on Factory Ramp-Up Performance

机译:工具安装延迟对工厂升级性能的影响

获取原文
获取原文并翻译 | 示例

摘要

This study examines the effect of delays in tool installation and qualification on plant performance, specified as discounted cumulative cash flow (DCCF), as the plant is ramped from zero to 20,000 wafer starts/month. Two different ramp strategies are addressed-conservative (24 months) and aggressive (9 months). A specific ramp analysis methodology using a discrete event simulator and cost and yield models, applied to the given assumption set, showed: (1) tool qualification delays impacted investment cost by $34 million/month before the fab breaks even and (2) opting for a 62.5% shorter ramp period effected a 19% reduction in break even time.
机译:这项研究考察了由于工厂从零增加到每月开始生产20,000片晶圆而导致的工具安装和资格认证延误对工厂性能的影响(指定为折现累计现金流量(DCCF))。保守(24个月)和激进(9个月)两种不同的应对策略。在给定的假设集合上使用离散事件模拟器以及成本和良率模型的一种特定的斜坡分析方法表明:(1)在晶圆厂收支平衡之前,工具鉴定延误对投资成本的影响为每月3400万美元,(2)选择斜坡时间缩短了62.5%,收支平衡时间减少了19%。

著录项

相似文献

  • 外文文献
  • 中文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号