Research of Abrasion Reason and Modifying Technigues of Wicket-gate Levers Installed in Three Gorges Hydropower Station

机译:三峡水电站闸门杠杆的磨损原因及改造技术研究

获取原文
获取原文并翻译 | 示例

摘要

There are 8 units with 700MW capacities, which are manufactured by ALSTOM, and installed in the left bank workshop of the Three Gorges Hydropower Station. After a year, there are 7 units that their bottom plate ring of 24 wicket-gate levers are all abraded, it is about 0.78mm in the most depth point. This paper analyzed detailedly abraded-reason of wicket-gate levers and summarize a principle of adjusting parallelism and modifying technigues and the parameter of machining 0Cr13Ni5Mo in according to the experience to modify this faults successfully.
机译:阿尔斯通制造的8台700MW机组安装在三峡水电站左岸厂房内。一年后,有7个单元的24个检票口杠杆的底板环全部磨损,最深点约为0.78mm。本文详细分析了闸门杠杆的磨损原因,总结了调整平行度和修改工艺的原理,并结合成功修改故障的经验总结了加工0Cr13Ni5Mo的参数。

著录项

相似文献

  • 外文文献
  • 中文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号