Lessons Learned from Large Decommissioning Projects

机译:大型退役项目的经验教训

获取原文
获取原文并翻译 | 示例

摘要

The lessons learned from large decommissioning projects may be summarized as follows: 1. Decommissioning planning should be initiated prior to shutdown in order to start decommissioning operations as early as possible.Licensing documents should be adapted to the new risk profile, which results in a significant reduction of the safety systems. 2. Waste storage areas should be provided with sufficient capacity at all times. Conditioning / storage of highly activated wastes will require specific auxiliary facilities. 3. Detailed characterization and management plans should be established for the different waste streams in order to ensure a fast and smooth logistic of materials. 4. Large containers should be used for highly activated/contaminated components in order to reduce segmentation costs and operator doses. 5. Segmentation of activated components should be performed by mechanical cutting in order to minimize secondary wastes. 6. Site remediation generates large volumes of material to be monitored and large amounts of very low level waste to be disposed. A well-established clearance process will contribute to the minimization of wastes resulting from remediation.
机译:大型退役项目的经验总结如下:1.应在停机之前启动退役计划,以便尽早开始退役操作。许可文件应适应新的风险状况,这将导致重大的事故。减少安全系统。 2.废物存储区应始终具有足够的容量。高活性废物的处理/存储将需要特定的辅助设施。 3.应为不同的废物流建立详细的表征和管理计划,以确保物料的快速,顺畅物流。 4.应使用大容器盛放高度活化/污染的部件,以减少分段成本和操作员剂量。 5.应该通过机械切割对活化成分进行分段,以最大程度地减少二次废物。 6.场地修复会产生大量要监控的材料,并会处理大量非常低水平的废物。完善的清除流程将有助于最大程度地减少由补救产生的废物。

著录项

相似文献

  • 外文文献
  • 中文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号