Pile Driving Indicator Program Results, Pier 400 Container Wharf, Port of Los Angeles, California

机译:加利福尼亚洛杉矶港码头400集装箱码头的打桩指示器计划结果

获取原文
获取原文并翻译 | 示例

摘要

The largest single-user container terminal in North America was recently constructed on Pier 400 at the Port of Los Angeles. The terminal's 2,250-meter long wharf is supported by about 3,700 24-inch octagonal precast, prestressed concrete piles. The piles are about 35-meters long and were driven through between 3 and 16 meters of rock dike. A total of 55 piles were monitored during two indicator pile-driving programs to develop the appropriate pile driving criteria to obtain the required axial pile capacity. The pile driving indicator programs include: 1) data from two different size diesel hammers and one hydraulic hammer, 2) comparison of piles driven dry versus those driven with jetting, and 3) restrike data after several days, several weeks, and several months. The results of the indicator pile programs provide the opportunity to better appreciate: 1) the impacts on capacity and schedule, when the piles are jetted, 2) the validity of using short-term restrikes to evaluate the ultimate long-term capacity of the piles, and 3) the potential economic, schedule, and quality control advantages that can be obtained when a hydraulic hammer is used.
机译:北美最大的单用户集装箱码头最近在洛杉矶港的400码头建造。该码头的2,250米长码头由大约3,700个24英寸八角形预制预应力混凝土桩支撑。桩长约35米,被打入3至16米的石堤之间。在两个指示桩驱动程序期间,总共监视了55个桩,以制定适当的打桩标准,以获得所需的轴向桩容量。打桩指示器程序包括:1)来自两个不同尺寸的柴油锤和一个液压锤的数据,2)比较干式驱动桩与喷射驱动桩的数据,以及3)几天,几周和几个月后的重击数据。指示桩计划的结果提供了更好地了解的机会:1)喷射桩时,对桩容量和进度的影响; 2)使用短期重载来评估桩的最终长期承载力的有效性,以及3)使用液压锤时可以获得的潜在的经济,进度和质量控制优势。

著录项

相似文献

  • 外文文献
  • 中文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号