Behavior of Reinforced Embankment on Soft Ground With and Without Jet Grouted Soil-Cement Piles

机译:带或不带喷射水泥土桩的软土地基加筋路堤性能

获取原文
获取原文并翻译 | 示例

摘要

Two full scale reinforced test embankments were constructed on soft Bangkok clay. Test Embankment 1 (TE1), 5.8 m height and reinforced with steel wire grids, was constructed over an unimproved soft ground. Test Embankment 2 (TE2), 6.0 m height and reinforced with hexagonal wire mesh, was constructed over a jet grouted soil-cement piles improved ground. After their construction, the maximum lateral movements in the foundation soils were 130 mm and 5 mm under TE1 and TE2, respectively. After one year of full embankment loading, the maximum settlement of TE1 was 1000 mm, while that of TE2 was only 325 mm; also, the maximum wall face lateral movements were 350 mm and 230 mm for TE1 and TE2, respectively. Moreover, the rate of consolidation settlement of TE2 is faster than TE1. Therefore, the installation of jet grouted soil-cement piles in the soft clay foundation has effected a suitable improvement in the engineering performances of the improved soft clay foundation and of the reinforced wall/embankment.
机译:在柔软的曼谷粘土上建造了两个全尺寸的增强测试路堤。 5.8 m高的测试路堤1(TE1)在不改善的软土地基上建造,并用钢丝网加固。测试堤2(TE2)高6.0 m,并用六角形金属丝网加固,建造在喷射注浆的水泥土桩上,改善了地面。构造后,在TE1和TE2下,基础土壤中的最大横向运动分别为130 mm和5 mm。路堤满载一年后,TE1的最大沉降量为1000 mm,而TE2的最大沉降量仅为325 mm。同样,TE1和TE2的最大壁面横向移动分别为350 mm和230 mm。而且,TE2的合并结算速度比TE1快。因此,在软粘土地基中安装喷射水泥土桩已经对改进的软粘土地基和加筋墙/路堤的工程性能进行了适当的改进。

著录项

相似文献

  • 外文文献
  • 中文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号