CASE HISTORY OF THE YORK ENERGY CENTER INTAKE/BLOWDOWN

机译:约克能源中心投入/排污的案例历史

获取原文
获取原文并翻译 | 示例

摘要

The York Energy Center project in Delta, PA consists of 565 megawatt generatingrnfacility that recovers heat from hot gas exhaust leaving gas turbines. The combustionrnturbines burn either natural gas or low sulfur diesel fuel oil. Combined, these two powerrncycles consume 70–80 percent of the fuel needed by a traditional fossil-fired boiler/rnsteam turbine generator plant. A microtunnel solution to installing the cooling waterrnintake and return was developed by the owner, contractor & tunnel subcontractor. Arn460 m × 1500 mm (1500 ft × 59 in) steel casing was jacked through rock and zero blowrncount river deposits that served as the intake. A 406 mm (16 in) HPDE line was installedrninside the casing to serve as a return. Financial and environmental considerations forrnthe microtunneling solution led to replacing the original twin pipeline trenched design.rnThe TBM was recovered from under Conowingo Lake along the Susquehanna River.
机译:宾夕法尼亚州三角洲的约克能源中心项目由565兆瓦的发电设施组成,该设施可从离开燃气轮机的热废气中回收热量。燃气轮机燃烧天然气或低硫柴油。这两个动力循环加起来消耗传统化石燃料锅炉/汽轮发电机组所需燃料的70%至80%。业主,承包商和隧道分包商开发了一种安装冷却水进水和回水的微隧道解决方案。 460 m×1500毫米(1500 ft×59英寸)的Arn钢套管被顶入岩石和零伯恩伯特河沉积物作为进水口。 406毫米(16英寸)HPDE管线安装在套管内,以作为回油口。微隧道解决方案的财务和环境考虑导致替换了原来的双管道开槽设计。隧道掘进机从萨斯奎哈纳河沿岸的科诺温戈湖下采出。

著录项

相似文献

  • 外文文献
  • 中文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号