首页> 外国专利> PT Potential Transformer Replacement Operation Standard Procedure and Temporary Power Supply Device Load Break Switches for Underground Line

PT Potential Transformer Replacement Operation Standard Procedure and Temporary Power Supply Device Load Break Switches for Underground Line

机译:PT电位变压器替换操作标准程序和临时电源设备负载断裂开关用于地铁线路

摘要

The ground switch PT replacement standardization method using the temporary power transmission device (1) of the present invention is based on the standard operation manual when the PT (Potential Transformer) 140 of the ground switch 100 is defective or damaged (S20) ,S30~S50/S30-1,S30-2,S100), temporary power transmission establishment (S60-1), defective PT on-site replacement (S70), and defective PT on-site inspection (S80) In the temporary transmission establishment state using (1), the on-site replacement of defective PT (S70) is constructed on-site according to the work procedure of the standard work manual, so it is possible to improve the safety/efficiency of the PT replacement and minimize the blackout time, especially the PT replacement standardization method Through the establishment of standard operation manual of
机译:当接地开关100的PT(电位变压器)140有缺陷或损坏时,使用本发明的临时动力传输装置(1)的地面开关PT替换标准化方法基于标准操作手册(S20),S30〜 S50 / S30-1,S30-2,S100),临时电力传输建立(S60-1),PT现场更换有缺陷(S70),以及使用的临时传输建立状态下的PT现场检查(S80)有缺陷 (1),根据标准工作手册的工作步骤,在现场安装有缺陷PT的现场更换(S70),因此可以提高PT更换的安全/效率,并最大限度地减少停电时间 ,尤其是PT替换标准化方法通过建立标准操作手册

著录项

  • 公开/公告号KR20210145429A

    专利类型

  • 公开/公告日2021-12-02

    原文格式PDF

  • 申请/专利权人 한국전력공사;

    申请/专利号KR20200062306

  • 发明设计人 김주현;박기옥;하보현;

    申请日2020-05-25

  • 分类号H01F27;H01F29/04;H02G1/02;H02G7/05;

  • 国家 KR

  • 入库时间 2022-08-24 22:36:21