摘要
PURPOSE: To complete concrete placement work requiring much trouble including form installation and bar arrangement by only one time of placement work of the concrete foundation, to enable work arrangements and work control and, at the same time, to reduce a construction period. ;CONSTITUTION: After a built-in scheduled place of the lower end 4a of a steel framed column 4 built-in and fixed to the concrete foundation 1 among concrete foundation developing scheduled places is separated from another place by a net-like form 3, concrete placement work of concrete foundation work is carried out. After the curing of a placed concrete, the lower end 4a of the steel framed column 4 is placed to a built-in scheduled place to place concrete 7 to the built-in scheduled place.;COPYRIGHT: (C)1993,JPO&Japio