首页> 外国专利> DRAFT PREVENTIVE CONSTRUCTION METHOD FOR CAISSON QUAY

DRAFT PREVENTIVE CONSTRUCTION METHOD FOR CAISSON QUAY

机译:沉箱码头预防性施工方法

摘要

PURPOSE: To establish a suck-out preventive method for caisson quay, which does not require skillful workers, can be completed through simple works, be embolied so as to suit the gap in a quay wall, allows shortening of the construction term because of no concrete placing process, and permits suppression of the construction costs and improving the economy. ;CONSTITUTION: A sack 3 is made from a synthetic fiber net, for example of nylon, and filled with crushed stones 4, and when a joint opening is generated in a causson embankment 1 at a caisson quay wall, the crushed stones 2 in such netting sacks are stacked in the joint opening so that the stop work is completed. Behind these stacked crushed stones 2, sandbags 5 are stacked, and further behind them, a sheet 6 is laid, behind which a backfill material 7 is deposited.;COPYRIGHT: (C)1996,JPO
机译:目的:建立不需要熟练工人的沉井码头防吸方法,可以通过简单的工作就可以完成,并进行浮雕以适合码头墙的空隙,从而可以缩短施工工期,因为没有混凝土浇筑过程,并可以抑制建筑成本并改善经济。组成:麻袋3由合成纤维网(例如尼龙)制成,并填充有碎石4,当在沉箱码头壁上的沉箱堤1中产生接合开口时,碎石2在这种情况下网袋被堆叠在接头开口中,从而完成了停止工作。在这些堆积的碎石2的后面堆积沙袋5,然后在沙袋5的后面放置一块薄板6,在其后面沉积回填材料7。版权所有:(C)1996,JPO

著录项

相似文献

  • 专利
  • 外文文献
  • 中文文献
获取专利

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号