PROBLEM TO BE SOLVED: To strongly connect an existing pile to a supplementary stud and perform connection work speedily and at low cost in using the existing pile as a foundation pile to construct the supplementary stud on the existing pile in a reverse concreting construction method for a large-scaled building. SOLUTION: In driving a foundation pile 1 under the ground surface at a building column standing position, and erecting a supplementary stud 2 on the foundation pile 1 to execute a reverse concreting construction method, an existing pile (steel pile) 1 is used as the foundation pile, and after driving this existing pile, concrete 3 is placed inside a head part of the existing pile 1, the supplementary stud 2 is constructed on the existing pile 1 using a supplementary stud erecting jig 15, and a lower part of the supplementary stud 2 is inserted into the concrete 3. Otherwise, the head part of the existing pile 1 and the lower part of the supplementary stud 2 are connected to each other to be fixed by a steel basket and concrete. Otherwise, the existing pile 1 and the supplementary stud 2 are preliminarily integrated, and after they are constructed, concrete is filled into the supplementary stud and the head part of the existing pile 1.
机译:解决的问题:将现有桩用作基础桩,以反向混凝土施工方法将现有桩作为基础桩将现有桩用作辅助桩,从而将现有桩牢固地连接至辅助桩,并以低成本快速进行连接工作。大型建筑。解决方案:在将建筑群立桩位置的地基桩1打入地面下方并在地基桩1上安装辅助螺柱2来执行反向混凝土施工方法时,将现有的桩(钢桩)1用作地基。在将基础桩打入基础桩后,将混凝土3放置在现有桩1的头部内部,并使用辅助螺栓竖立夹具15在现有桩1上构造辅助螺柱2,并在下部安装下部桩将螺柱2插入混凝土3中。否则,将现有桩1的头部和辅助螺柱2的下部彼此连接,并用钢筐和混凝土固定。否则,将现有桩1和辅助螺柱2预先集成在一起,并且在将它们建造之后,将混凝土填充到现有桩1的辅助螺柱和头部中。

著录项

相似文献

  • 专利
  • 外文文献
  • 中文文献
获取专利

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号