首页> 外国专利> - The advanced method for arrangement of prefabricated reinforcement for each span for Movable Scaffolding System in the double-T girder bridge

- The advanced method for arrangement of prefabricated reinforcement for each span for Movable Scaffolding System in the double-T girder bridge

机译:-双T梁桥的活动脚手架系统每个跨度的预制钢筋布置的先进方法。

摘要

PURPOSE: An installation method by prefabrication of reinforcing bars by spans when constructing a double-T bridge by a movable scaffolding system is provided to improve constructability, to shorten a period of construction and to improve the quality of construction. CONSTITUTION: The installation method by prefabrication of reinforcing bars by spans when constructing a double-T bridge by a movable scaffolding system comprises the steps of: after installing a rail for moving a reinforcement jig on the top of the pre-placed bridge, installing a reinforcement jig on the rail; arranging reinforcing bars by spans on the installed reinforcing jig, then assembling a sheath tube; after completing the assembly of the reinforcing bars and the sheath tube, executing inspection; fastening the reinforcement jig to a spreader beam in a reinforcement jig by a hoist, then lifting; and installing the lifted reinforcement jig on the movable scaffolding form using a hoist, and moving a movable unit of the reinforcement jig to the assembling position of reinforcing bars and assembling reinforcing bars for installing on the next span.
机译:目的:提供一种通过用活动式脚手架系统建造双T形桥时通过跨度预制钢筋的安装方法,以提高可施工性,缩短施工周期并提高施工质量。组成:通过活动式脚手架系统建造双T形桥时,通过跨度预制钢筋的安装方法包括以下步骤:在用于将钢筋夹具移动到预先放置的桥的顶部的轨道上安装后,安装一个轨道上的加固夹具;在已安装的钢筋夹具上跨度布置钢筋,然后组装护套管。完成钢筋与护套管的组装后,进行检查;用提升机将加固夹具固定在加固夹具中的吊具梁上,然后提升;使用提升机将提升的钢筋夹具安装在可移动的脚手架模板上,并将钢筋夹具的可移动单元移动到钢筋的组装位置,并组装用于在下一个跨度上安装的钢筋。

著录项

相似文献

  • 专利
  • 外文文献
  • 中文文献
获取专利

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号