首页> 外国专利> PSC Constructing Method of Continuous PSC Girder Bridges Using Multi-stepwise Thermal Prestressing Method

PSC Constructing Method of Continuous PSC Girder Bridges Using Multi-stepwise Thermal Prestressing Method

机译:多步热预应力法连续PSC梁桥的PSC施工方法

摘要

PURPOSE: A continuation method of a PSC beam bridge using a multi-stage temperature prestressing method is provided to offset the stress caused by dead load and live load on an inner spot of continuous PSC beam bridges and to continue PSC beam bridges by increasing structural section by a lateral gusset plate. CONSTITUTION: The continuation method of a PSC beam bridge using a multi-stage temperature prestressing method comprises the steps of: installing a high-tensile bolt fixing plate(2) to anchor a steel lateral gusset plate(5) on the top of a PSC beam for continuation; placing the PSC beam attached with the high-tensile bolt fixing plate(2) on the spot for continuation; placing the steel lateral gusset plate(5), then supplying a heat source to generate artificial multi-stage temperature distribution to cause temperature transformation; continuing PSC beams by fastening the high-tensile bolt fixing plate(2) and the lateral gusset plate in a job site, removing the artificial temperature distribution by stopping heating up, offsetting the section force by dead load and live load which act on an inner spot of the continuous PSC beams by the section force by shrinkage of the lateral gusset plate caused by a fall in temperature, and increasing structural section of a continued part by the lateral gusset plate; replacing a temporary support of the PSC beam with a regular support installed on the continued spot if necessary; arranging reinforcing bars for a floor slab, placing a high-tensile bolt fixing plate(2) to be installed on the top of a floor slab, then placing floor slab concrete; and installing a lateral gusset plate on the side of the PSC beam or the floor slab, then applying temperature prestress again.
机译:目的:提供一种采用多阶段温度预应力法的PSC梁桥的延续方法,以抵消由静载和活载引起的连续PSC梁桥内点的应力,并通过增加结构截面来延续PSC梁桥通过侧面的角撑板。组成:采用多阶段温度预应力法的PSC梁桥的延续方法包括以下步骤:安装高强度螺栓固定板(2),以将钢质侧向角撑板(5)锚固在PSC的顶部连续光束将附有高强度螺栓固定板(2)的PSC横梁放在现场继续进行;放置侧向角撑板(5),然后提供热源以产生人为的多阶段温度分布,从而引起温度变化;通过将高强度螺栓固定板(2)和侧向角撑板固定在工作现场中来连续PSC梁,通过停止加热来消除人为的温度分布,通过作用在内部的静载荷和活载荷抵消截面力由于温度下降引起的横向角撑板收缩而产生的截面力引起的连续PSC梁的光斑,以及通过横向角撑板增大连续部分的结构截面。必要时,将PSC梁的临时支撑替换为在现场连续安装的常规支撑;布置地板的钢筋,在地板的顶部放置一个要安装的高强度螺栓固定板(2),然后放置混凝土的地板;然后在PSC横梁或楼板的侧面安装侧向角撑板,然后再次施加温度预应力。

著录项

  • 公开/公告号KR20030055061A

    专利类型

  • 公开/公告日2003-07-02

    原文格式PDF

  • 申请/专利权人 KIM SANG HYO;

    申请/专利号KR20010085516

  • 发明设计人 KIM SANG HYO;

    申请日2001-12-26

  • 分类号E01D2/00;

  • 国家 KR