PPROBLEM TO BE SOLVED: To provide an earth retaining method using soldier piles and horizontal sheet piles, which is carried out by quickly covering an exposed excavated wall surface with the horizontal sheet piles, and quickly bringing the latter into tight contact with the former, to thereby avoid loosening of the ground around the construction site. PSOLUTION: The earth retaining method using the soldier piles and horizontal sheet piles, which employs H beams 11 as the soldier piles, is comprised of the following steps. In the first step, flanges 12 of the respective H beams are arranged along the earth retaining wall surface to be constructed, and embedded in the ground. In the following step, messer steel plates 10 each having a width equal to an interval between the pairing flanges 12 adjacent to each other, are arranged on a rear side of the flanges, and while each messer steel plate is moved downward with a gap secured between the messer steel plate and a rear surface 12a, excavation is carried out on a front side of the flanges 12. In the last step, each horizontal sheet pile 13 is inserted and arranged in the gap between rear surfaces 12a of the flanges 12 and the messer steel plate 10 via both ends thereof to be held along a front surface of the messer steel plate 10, and after downward movement of the messer steel plate 10, the horizontal sheet piles cover the excavated wall surface which is exposed to the outside in an area above the messer steel plate 10, followed by driving wedge members 15 to the horizontal sheet piles 13 to fasten the horizontal sheet piles 13 to the excavated wall surface. PCOPYRIGHT: (C)2006,JPO&NCIPI
机译:

要解决的问题:提供一种使用士兵桩和水平板桩的挡土方法,该方法是通过用水平板桩快速覆盖裸露的开挖墙面,并使水平板桩迅速与地面紧密接触来实现的。前者,从而避免施工现场周围的地面松动。

解决方案:使用士兵桩和水平板桩的挡土方法采用H型钢11作为士兵桩,该方法包括以下步骤。在第一步中,各个H梁的凸缘12沿着要构造的挡土墙表面布置,并埋入地下。在接下来的步骤中,将宽度彼此相邻的配对凸缘12之间的间隔相等的宽度的碟形钢板10布置在凸缘的后侧,并且在使每个碟形钢板向下移动的同时确保间隙。在法兰盘12的前侧和斜盘之间,在法兰盘12的前侧进行挖掘。在最后一步中,将每个水平板桩13插入并布置在法兰盘12的后表面12a之间的间隙中。墨斗钢板10的两端沿墨斗钢板10的前表面被保持,并且在墨斗钢板10向下移动之后,水平板桩覆盖暴露于外部的挖出的壁表面。然后,在楔形钢板10上方的一个区域中,将楔形构件15驱动到水平板桩13上,以将水平板桩13固定到挖掘的壁表面上。

版权:(C)2006,JPO&NCIPI

著录项

  • 公开/公告号JP2006104782A

    专利类型

  • 公开/公告日2006-04-20

    原文格式PDF

  • 申请/专利权人 OKUMURA CORP;

    申请/专利号JP20040293418

  • 发明设计人 YASUHARA KEIJI;MURAI MICHITADA;

    申请日2004-10-06

  • 分类号E02D17/04;E02D5/02;

  • 国家 JP

  • 入库时间 2022-08-21 21:53:26

相似文献

  • 专利
  • 外文文献
  • 中文文献
获取专利

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号