首页> 外国专利> BAR ARRANGEMENT POSITION OF VERTICAL REINFORCEMENT OR SHEARING REINFORCEMENT, AND IMPROVEMENT TO SQUARE-PIPE TYPE STEEL LEG, ONE-LEG TYPE STEEL LEG, COVER-PLATE TYPE STEEL LEG AND HIGH-LEG TYPE STEEL LEG FOR INCREASING CONSTRUCTION EFFICIENCY IN CONSTRUCTION METHOD OF MAT FOUNDATION BY CONNECTION BETWEEN CONCRETE FOUNDATION BEAM MEMBER AND MEMBER FOR CONNECTING CONCRETE FOUNDATION BEAM PART

BAR ARRANGEMENT POSITION OF VERTICAL REINFORCEMENT OR SHEARING REINFORCEMENT, AND IMPROVEMENT TO SQUARE-PIPE TYPE STEEL LEG, ONE-LEG TYPE STEEL LEG, COVER-PLATE TYPE STEEL LEG AND HIGH-LEG TYPE STEEL LEG FOR INCREASING CONSTRUCTION EFFICIENCY IN CONSTRUCTION METHOD OF MAT FOUNDATION BY CONNECTION BETWEEN CONCRETE FOUNDATION BEAM MEMBER AND MEMBER FOR CONNECTING CONCRETE FOUNDATION BEAM PART

机译:竖向钢筋或剪切钢筋的钢筋布置位置,以及对方管型钢脚,单腿型钢脚,盖板型钢脚和高腿型钢脚的改进,以提高施工方法的施工效率通过混凝土基础梁构件与连接混凝土基础梁构件的构件之间的连接

摘要

PROBLEM TO BE SOLVED: To solve the problems for saving labor and increasing efficiency at a construction site, that efforts of performing allocation confirmation by applying a scale every time and also efforts of confirming the position of a reinforcement following it need to be eliminated, and that setting of a pitch becomes limited because of a form, which necessarily includes the loss of cost, while there are inconveniences in a low position, congestion in a narrow space, the vertical relationship of the reinforcements, handling of a long reinforcement, etc. if the work is performed after bottom-slab reinforcement and lower main reinforcement products are carried in and installed.;SOLUTION: By arranging a projection position of the vertical reinforcement or the shearing reinforcement 2 which are projected from a precast product within the trowel surface, namely, by preventing the vertical reinforcement or the shearing reinforcing bar 2 from passing through a hole in the side plate of the form, the setting of the pitch or the like is made flexible, while having an advantage on calculation of bending moment which is determined in the center of the base. Furthermore, in order to assemble all of the bottom-slab reinforcements and the lower main reinforcements before the concrete foundation beam member is carried in and installed, a one-leg type, a cover-plate type, and a high-leg type are adopted as an abbreviated and simple steel leg which can squeeze through the bar arrangement pitch of the reinforcement.;COPYRIGHT: (C)2011,JPO&INPIT
机译:要解决的问题:为了解决在建筑工地节省劳力和提高效率的问题,需要消除通过每次使用比例尺来进行分配确认的工作,以及消除在钢筋之后确定钢筋位置的工作,以及节距的设置由于形式而受到限制,形式必然包括成本的损失,同时在低位置处带来不便,狭窄空间中的拥挤,增强件的垂直关系,长增强件的处理等。如果在下层钢筋和下部主钢筋产品被搬入并安装后进行工作;那么解决方案:通过将从预制产品投射的垂直钢筋或剪切钢筋2的投射位置布置在泥铲表面,即,通过防止竖直钢筋或剪切钢筋2穿过侧板o中的孔,在该形式中,节距等的设定是灵活的,同时在计算弯矩方面具有优势,该弯矩是在基座的中心确定的。此外,为了在搬入和安装混凝土基础梁构件之前组装所有的底部平板增强件和下部主增强件,采用了单腿型,盖板型和高腿型。作为一种简洁的钢制腿,可以挤压钢筋的钢筋排列间距。;版权所有:(C)2011,JPO&INPIT

著录项

相似文献

  • 专利
  • 外文文献
  • 中文文献
获取专利

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号