FIELD: mining.;SUBSTANCE: method in which the quarry along the length is divided by the lines, of which the first is worked out to a target depth with an external spoil disposal and working out of the subsequent ones is carried out using an internal spoil disposal, placing the overburden in the mined-out space of the adjacent line with the common formation of the dump tiers with the development of mining work. And simultaneously with the start of mining operations in the quarry of the first stage within the quarry of the second stage along the deposits the front quarry is built with angles of the slopes of sides close to the angles of reclamation, the cross-overs are located in it for providing cargo communication of the upper working horizons of the quarry of the first stage with the surface, with the reduction of mining operations in the quarry of the first stage on its longitudinal side the loop cross-overs are made adjacent to the bottom of the quarry in the area of the end side, which is formed with a slope towards the temporary side, marking the limit of the quarries of first and second stage, when achievement in the mining operations in the quarry of the first stage of the current depth. The separation of the sides of the front quarry is carried out, turning them into working, and after complete working out the reserves of the quarry of the first stage the working out the reserves of the quarry of the second stage is carried out, while linking its main openings to the main openings of quarry of the first stage in the locations of the loops, the inner dump in the worked-out area of quarry of the first stage is formed as inclined and horizontal tiers, at first directly with the surface from the side not occupied with main openings, the inclined tier is made with bulldozers with width of the platform on top equal to zero, and then using a draglines it is extended by the amount of boom extension, after this the horizontal tiers are dumped in series from the bottom up from the loop cross-overs with the high ensuring their sustainability, to complete formation of the inner dump.;EFFECT: decrease in the distance of inner transportation of overburden from the working area to the inner dump.;8 dwg
机译:领域:采矿;实体:沿着长度将采石场除以线的方法,其中第一个通过外部弃渣处理达到目标深度,然后使用内部弃具进行处理弃渣处理,随着采矿工作的发展,将覆盖层放置在相邻管线的采空区,形成倾卸层。在开始第二阶段采石场内第一阶段采石场沿矿床的采矿作业的同时,建造前采石场时边坡的角度接近填海角度,跨界线位于其中用于提供第一阶段采石场上部工作面与地面之间的货物通讯,同时减少了第一阶段采石场纵向的采矿作业,使回路交叉点靠近底部在当前一侧第一阶段采石场的采矿作业取得成功时,在朝向临时一侧倾斜的端侧区域采石场的坡度,这标志着第一阶段和第二阶段采石场的极限。深度。进行前采石场两侧的分离,将它们转变为工作状态,并在完成第一阶段采石场的储量计算之后,进行第二阶段采石场的储量的计算其主要开口到第一阶段采石场的主要开口在环路的位置,第一阶段采石场工作区域的内部垃圾场形成为倾斜层和水平层,首先直接从地面在没有主要开口的一侧,用推土机制造倾斜层,其顶部的平台宽度等于零,然后使用拉铲将其扩展成动臂延伸量,然后将水平层依次倾倒从下至上,从高处穿过环行交叉路口,确保其可持续性,完成内部垃圾场的形成。效果:减少了覆盖层从工作区域到t的内部运输距离他内心的垃圾。; 8 dwg

著录项

相似文献

  • 专利
  • 外文文献
  • 中文文献
获取专利

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号