首页> 外国专利> TOP-DOWN PILE CONSTRUCTION METHOD USING DETACHABLE BEARING UNIT AND TOP-DOWN CONSTRUCTION METHOD USING SAME

TOP-DOWN PILE CONSTRUCTION METHOD USING DETACHABLE BEARING UNIT AND TOP-DOWN CONSTRUCTION METHOD USING SAME

机译:使用可拆卸轴承单元的自下而上桩法和使用相同方法的自下而上法桩

摘要

The present invention relates to a top-down pile construction method using a detachable bearing unit, and a top-down construction method using the same. A detachable bearing unit and a large diameter PHC pile supporting a load of a structure and a work load of a basement layer are constructed by being connected in the top-down construction method, and a steel pillar is connected to the PHC pile by being inserted into the detachable bearing unit to conduct excavation construction. As such, the top-down pile construction method using the detachable bearing unit is able to remarkably reduce pile construction costs in a top-down section. According to a desirable embodiment of the present invention, the top-down pile construction method using the detachable bearing unit comprises: (a) a step of boring a bored hole in a predetermined depth; (b) a step of forming a reinforcing plate and embedding the detachable bearing unit which is coupled as a coupling unit of the reinforcing plate is coupled to a connection bolt of the PHC pile of a joint unit into the bored hole; (c) a step of lightly hitting an upper end of the detachable bearing unit, and embedding a front end of the lower PHC pile into a support layer; (d) a step of inserting the steel pillar having a plurality of stud bolds on the outside of a lower part, into a hollow of the bearing unit, and embedding a lower end to the PHC pile of the joint unit; (e) a step of injecting grout into the PHC pile of the joint unit; (f) a step of disassembling the detachable bearing unit from the PHC pile, and drawing out the bearing unit to the outside; and (g) a step of refilling the bored hole with soil.;COPYRIGHT KIPO 2017
机译:本发明涉及一种使用可拆卸轴承单元的自上而下的桩施工方法,以及使用该方法的自上而下的施工方法。通过自顶向下的施工方法,将可拆卸的轴承单元和支撑结构的载荷以及基底层的工作载荷的大直径PHC桩连接起来,并通过插入将钢柱连接到PHC桩上进入可拆卸轴承单元进行挖掘施工。这样,使用可拆卸轴承单元的自上而下的桩施工方法能够显着降低自上而下的部分中的桩施工成本。根据本发明的一个优选实施例,使用可拆卸轴承单元的自顶向下的桩施工方法包括:(a)在预定深度钻孔的步骤; (b)形成加强板并将将作为加强板的连接单元而被连接的可拆卸轴承单元嵌入到连接单元的PHC桩的连接螺栓上的孔中的步骤; (c)轻轻敲打可拆卸轴承单元的上端,并将下部PHC桩的前端嵌入支撑层的步骤; (d)将在下部的外侧具有多个双头螺栓的钢制支柱插入轴承单元的凹部,并将下端埋设于接头单元的PHC桩的工序。 (e)将水泥浆注入到接头单元的PHC桩中的步骤; (f)从PHC桩上拆卸可拆卸轴承单元,并将轴承单元向外拉出的步骤; (g)用土壤填充钻孔的步骤。COPYRIGHTKIPO 2017

著录项

  • 公开/公告号KR101766165B1

    专利类型

  • 公开/公告日2017-08-10

    原文格式PDF

  • 申请/专利权人 KWON JUNG HEE;

    申请/专利号KR20160167944

  • 发明设计人 KWON JUNG HEEKR;

    申请日2016-12-09

  • 分类号E02D5/58;E02D5/52;

  • 国家 KR

  • 入库时间 2022-08-21 13:25:02