Time and work generalised precedence relationships in project scheduling with pre-emption: An application to the management of Service Centres

机译:具有优先权的项目计划中的时间和工作通用优先关系:服务中心管理中的应用

获取原文
获取原文并翻译 | 示例
   

获取外文期刊封面封底 >>

       

摘要

In this paper we present an application of project scheduling concepts and solution procedures for the solution of a complex problem that comes up in the daily management of many company Service Centres. The real problem has been modelled as a multi-mode resource-constrained project scheduling problem with pre-emption, time and work generalised precedence relationships with minimal and maximal time lags between the tasks and due dates. We present a complete study of work GPRs which includes proper definitions, a new notation and all possible conversions amongst them. Computational results that show the efficiency of the proposed hybrid genetic algorithm and the advantages of allowing pre-emption are also presented.
机译:在本文中,我们提出了项目进度计划概念和解决程序的应用程序,用于解决许多公司服务中心的日常管理中出现的复杂问题。实际问题已被建模为具有抢先,时间和工作的通用优先级关系的多模式资源受限的项目计划问题,任务与到期日之间的时间间隔为最小和最大。我们对工作GPR进行了完整的研究,其中包括正确的定义,新的表示法以及其中所有可能的转换。计算结果表明了所提出的混合遗传算法的效率以及允许先占的优势。

著录项

相似文献

  • 外文文献
  • 中文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号