首页> 外文期刊>Production Planning & Control >The impact of make-ready process on project cost performance in heavy civil construction projects
【24h】

The impact of make-ready process on project cost performance in heavy civil construction projects

机译:制备工艺对重型民用建设项目项目成本绩效的影响

获取原文
获取原文并翻译 | 示例
           

摘要

The research investigates the relationship between the production plan reliability and the project cost performance using project data in the heavy civil construction sector. The research also investigates the attributes of a make-ready process using the statistical analysis. This study shows that production planning reliability (i.e. Per cent Constraint Removal (PCR) and Per cent Plan Complete (PPC)) and project cost performance (CPI) are significantly correlated in the heavy construction projects. The findings show that there is a more significant correlation between production planning reliability and project cost performance in project-scaled data than in monthly scaled data. They suggest that there is a time-lag between when the variance of workflow occurs and when the workflow variance impacts on the project cost performance. The result of the analysis also shows that the measure of make-ready process, PCR, has a more significant correlation with the project cost performance than the measure of weekly plan reliability, PPC.
机译:研究通过重型民用建设部门的项目数据调查了生产计划可靠性与项目成本绩效之间的关系。研究还使用统计分析调查制备工艺的属性。本研究表明,生产规划可靠性(即百分比约束(PCR)和百分比计划完整(PPC))和项目成本绩效(CPI)在重型建设项目中具有显着相关。调查结果表明,在项目缩放数据中生产规划可靠性和项目成本性能之间的相关性更为显着相关性,而不是月度缩放数据。他们建议在工作流程的差异以及工作流程方差对项目成本性能产生时,存在时间滞后。分析结果还表明,制备过程PCR的量度与项目成本性能更为显着相关性,而不是每周计划可靠性PPC。

著录项

相似文献

  • 外文文献
  • 中文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号