This paper provides a detailed study of remediation work on the core zone of a damaged earth-fill dam. The relevant material includes a review of the dam surface survey data, leakage monitoring data, drilling method, grouting material, and drilling and grouting procedure. A compaction grouting method was selected as the remediation technique. In addition, the reduction and prevention of leakage and settlement were assessed. Compaction grouting was successful for filling voids, closing channels, and compacting the disturbed core soils. The loose or voided zones were properly filled, and the leakage was reduced after compaction grouting. Verification of the compaction grouting work was performed by evaluating the grouting pressures and volumes injected internally and by monitoring the dam leakage rate and tracer externally. All of these factors provide a good indication of changes inside the core of the dam, including reduction or closure of the leakage channels in the dam core.
机译:本文提供了对受损土石坝核心区修复工作的详细研究。相关材料包括对大坝表面调查数据,泄漏监测数据,钻探方法,灌浆材料以及钻探和灌浆程序的审查。选择了压实灌浆方法作为修复技术。此外,还评估了减少和防止泄漏和沉降的方法。压实灌浆成功地填充了空隙,封闭了通道并压实了受干扰的岩心。适当填充疏松或空隙区域,并在压实灌浆后减少渗漏。压实注浆工作的验证是通过评估内部注浆压力和注浆量以及通过外部监测大坝渗漏率和示踪剂来进行的。所有这些因素都很好地表明了坝心内部的变化,包括减少或关闭了坝心中的泄漏通道。

著录项

相似文献

  • 外文文献
  • 中文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号