首页> 外文期刊>Tunnelling & Trenchless Construction >TBMs raise work rate again at Karahnjukar
【24h】

TBMs raise work rate again at Karahnjukar

机译:图班人的愤怒工作率再次和Karahanjkar

获取原文
获取原文并翻译 | 示例
           

摘要

AFTER several weeks of slow progress due to difficult ground conditions, the three Bobbins tunnel-boring machines (TBMs) drilling the main headrace tunnel at Iceland's Karahnjukar hydro-electric project are generally making good progress again. April saw steady advances by all three machines, which had been held up previously due to the necessity to install extra support (full steel rings with mesh and shotcrete) immediately behind them. However, the work rates of TBMs 2 and 3 have slowed down since the beginning of May since they have encountered more bad ground. Drill and blast operations are now under way at both ends of the Ufsarlon headrace tunnel employing Impregilo's Sandvik Tamrock Axera drill rigs. Some 650 m have been driven, mostly at one end; drilling only began at the other end in late April. Progress on this section should improve rapidly. It is planned to drive 3,500 m by drill and blast. After this, it will be possible to use one of the TBMs drilling the main headrace tunnel to complete this section.
机译:由于恶劣的地面条件,工程进展缓慢,持续了数周,三台Bobbins隧道掘进机(TBM)在冰岛Karahnjukar水力发电项目的主要水道隧道中钻探,总体上又取得了良好进展。四月份,所有三台机器均取得了稳定的进步,由于必须在其后方安装额外的支撑(带有网眼和喷射混凝土的全钢环),之前一直受阻。但是,自5月初以来,TBM 2和3的工作效率有所降低,因为它们遇到了更多的不利情况。目前,正在使用Impregilo的Sandvik Tamrock Axera钻机在Ufsarlon头枕隧道的两端进行钻探和爆破作业。大约有650 m被驱动,大部分在一端。钻探仅在四月下旬开始。本节的进展应迅速改善。计划通过钻孔和爆破驱动3500 m。此后,将可以使用其中一个钻进主头水道隧道的TBM来完成此部分。

著录项

相似文献

  • 外文文献
  • 中文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号