...
首页> 外文期刊>Water >THE VICTORIAN DESALINATION PLANT'S WATER TRANSFER SYSTEM
【24h】

THE VICTORIAN DESALINATION PLANT'S WATER TRANSFER SYSTEM

机译:维多利亚海水淡化厂的输水系统

获取原文
获取原文并翻译 | 示例
           

摘要

The Victorian Desalination Plant is the largest desalination plant built in Australia. The Public Private Partnership project was awarded to AquaSure in July 2009; AquaSure then contracted the Thiess Degremont Joint Venture to deliver the design, construction and commissioning. Thiess Degremont subcontracted the water transfer pipeline and the high voltage cables to a joint venture between themselves and Nacap Australia Pty Ltd, a specialist pipeline constructor. The design and construction began under an accelerated engineering, procurement, construction and commissioning (EPCC) program. The scope for the EPCC of the water transfer system began simultaneously with that of the desalination plant. The water transfer system enabled the desalinated water to be transferred from the plant in Wonthaggi to a Melbourne Water network connection at Berwick and, ultimately, to Melbourne Water's Cardinia reservoir. The scope of the EPCC included the approximately 2m-diameter mild steel cement-lined (MSCL) transfer pipeline over an 84km length with a capacity of 200 GL per annum; transfer pump station to convey up to 150 GL per annum; booster pump station; surge mitigation system to withstand pressures of up to 3,000 kPa and vacuum conditions; 87km of 220kV high-voltage below-ground electrical cables in trefoil configuration; two separate fibre optic cables and appurtenances along the pipeline easement. Precision planning by the project team was critical to the successful management of simultaneous challenges throughout the project delivery phases, including: 1. Implementing an intensive community and stakeholder engagement program to minimise the impact on the community; 2. Ensuring stringent environmental guidelines were achieved; 3. Undertaking a thoughtful procurement strategy and construction program to manage long lead items; 4. Completing engineering in accordance with project requirements and obtaining certification under an independent review process to allow procurement and construction to commence; 5. Ensuring the requirements of multifaceted durability were achieved; 6. Designing and implementing large-scale traffic management plans to ensure the smooth delivery of the many thousands of construction components and minimise impact on roads and traffic; 7. Planning for construction of the pipeline in flood-prone areas with varying geology, topography and conditions (such as acid sulphate soils) to ensure compliance with regulations. The approach taken by the multi-disciplinary team meant that the project was delivered to the highest quality, meeting contract and stakeholder requirements and with an outstanding safety record. This paper highlights the major challenges in delivering this critical infrastructure from engineering, procurement, construction and commissioning points of view.
机译:维多利亚式海水淡化厂是澳大利亚建造的最大的海水淡化厂。 2009年7月,AquaSure获得了“公共私人合作伙伴关系”项目;然后,AquaSure与Thiess Degremont合资企业签约,以进行设计,建造和调试。 Thiess Degremont将输水管道和高压电缆分包给他们自己与专业管道建设商Nacap Australia Pty Ltd之间的合资企业。根据加速的工程,采购,建造和调试(EPCC)计划,开始了设计和建造。输水系统的EPCC范围与海水淡化厂的范围同时开始。输水系统使淡化水从Wonthaggi的工厂转移到Berwick的Melbourne Water Network连接点,最终到Melbourne Water的Cardinia水库。 EPCC的范围包括一条长约84 km的直径约2m的低碳钢水泥衬里(MSCL)输送管道,年产能为200 GL;输送泵站,每年输送多达150 GL;增压泵站;浪涌缓解系统可承受高达3,000 kPa的压力和真空条件;三叶配置的87kV 220kV高压地下电缆;沿管道缓和处的两条独立的光纤电缆和附件。项目团队的精确计划对于成功管理整个项目交付阶段中同时存在的挑战至关重要,包括:1.实施密集的社区和利益相关方参与计划,以最大程度地减少对社区的影响; 2.确保达到严格的环境准则; 3.制定周到的采购策略和建设计划,以管理长铅项目; 4.根据项目要求完成工程并通过独立审查程序获得认证,以允许采购和施工开始; 5.确保达到多方面的耐久性要求; 6.设计和实施大规模的交通管理计划,以确保数千个建筑组件的顺利交付并最大程度地减少对道路和交通的影响; 7.计划在地质,地形和条件各异的易洪灾地区(例如酸性硫酸盐土壤)建设管道,以确保遵守法规。多学科团队采用的方法意味着该项目以最高质量交付,满足合同和利益相关者的要求,并拥有出色的安全记录。本文从工程,采购,建筑和调试的角度强调了交付这一关键基础架构的主要挑战。

著录项

相似文献

  • 外文文献
  • 中文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号