Canada Toronto Hydro-Electric System Limited announced on 5 February the Dibco TBM has arrived. Additionally, it is already being readied to begin tunnelling north to connect Canada's second underground transformer station to the grid. The TBM will be on-site at Copeland Station for approximately three months, as it digs 600m to join the existing transmission tunnel beneath the intersection of Lower Simcoe and Front Streets.
机译:加拿大多伦多水电系统有限公司于2月5日宣布Dibco TBM已到达。此外,已经准备开始向北开挖隧道,以将加拿大的第二个地下变电站连接到电网。 TBM将在谷轮站现场停留大约三个月,挖出600m,与下Simcoe和Front Streets交汇处下方的现有传输隧道连接。