This paper examines 'availability' and the input metrics of operational expenditure (OPEX) for wave energy projects and reports on a case study which assesses the impact of these inputs on project profit returns. Case study simulations modelled a 75 MW wave energy project at two locations; the west coast of Ireland and the north coast of Portugal. Access and availability with respect to weather windows at both locations are discussed and their impact on energy output and wave farm operations is quantified. The input metrics used to calculate OPEX of wave energy projects are defined as well as the impact of OPEX on project net present value (NPV) and internal rate of return (IRR). Results indicate that access and resultant availability factors have a significant impact on case study results by reducing energy output and correspondingly financial returns. Furthermore, the technology maturity level designated for a project also impacts on availability factors and consequently energy output and NPV. Case study profits proved to be very sensitive to annual OPEX, especially if overhaul and replacement costs were accounted for. As a result of the impact of 'availability' on project profit returns, Feed-in tariffs will need to be tailored to the location in question as well as the device technology maturity level, with case study simulations indicating that high FIT will be required to support early stage WEC projects.
机译:本文研究了波浪能项目的“可用性”和运营支出的输入指标(OPEX),并报告了一个案例研究,该案例评估了这些投入对项目利润回报的影响。案例分析模拟了两个地点的75兆瓦波浪能项目;爱尔兰的西海岸和葡萄牙的北海岸。讨论了两个位置的天气窗口的可访问性和可用性,并量化了它们对能源输出和波浪农场运营的影响。定义了用于计算波浪能项目运营成本的输入指标,以及运营成本对项目净现值(NPV)和内部收益率(IRR)的影响。结果表明,获取和产生的可用性因素通过减少能源输出和相应的财务回报,对案例研究结果产生了重大影响。此外,为项目指定的技术成熟度水平也会影响可用性因素,从而影响能量输出和NPV。案例研究的利润被证明对年度运营支出非常敏感,特别是如果考虑了大修和更换成本。由于“可用性”对项目利润回报的影响,上网电价将需要针对相关地点和设备技术成熟度进行量身定制,案例研究模拟表明,需要高FIT才能实现。支持早期的WEC项目。

著录项

  • 来源
    《Renewable energy》 |2013年第2期|1119-1131|共13页
  • 作者

    M. OConnor; T. Lewis G. Dalton;

  • 作者单位

    Hydraulics and Maritime Research Centre (HMRC), University College Cork, Youngline industrial Estate. Togher, Cork, Ireland;

    Hydraulics and Maritime Research Centre (HMRC), University College Cork, Youngline industrial Estate. Togher, Cork, Ireland;

  • 收录信息 美国《科学引文索引》(SCI);美国《工程索引》(EI);
  • 原文格式 PDF
  • 正文语种 eng
  • 中图分类
  • 关键词

    access; availability; O/M; feed-in tariff; cost of electricity;