【24h】

NLL resignalling delay

机译:NLL重新签名延迟

获取原文
获取原文并翻译 | 示例
       

摘要

Freight operators using orbital routes across north London face a further seven months of delays, because work to remodel the four-track section of the North London Line between Dalston Western Junction and Camden Road East Junction will not be completed as planned during the current 101-day blockade.rnOriginally, the NLL was expected to close from January to April with the passenger service suspended between Gospel Oak and Stratford (RB1341 p3), but this blockade was postponed and is currently in force from February 20 to May 31.rnDuring this period, wholesale track and signalling renewals were to be carried out, and the layout altered on the 3 miles between Camden and Dalston to segregate NLL services from East London Line trains to Highbury ft Islington.
机译:货运运营商使用穿越伦敦北部的轨道路线面临另外七个月的延误,因为改造Dalston Western Junction和Camden Road East Junction之间的North London Line四轨路段的工作将无法按计划在目前的101-最初,NLL预计于1月至4月关闭,而福音橡树和斯特拉特福德之间的客运服务暂停(RB1341 p3),但这一封锁已被推迟,目前从2月20日至5月31日生效。 ,将进行批发轨道和信号灯的更新,并且在卡姆登(Camden)和达尔斯通(Dalston)之间的3英里处进行了布局更改,以分隔从东伦敦线列车到海布里·伊斯灵顿的NLL服务。

著录项

  • 来源
    《Rail business intelligence》 |2010年第362期|3|共1页
  • 作者

  • 作者单位
  • 收录信息
  • 原文格式 PDF
  • 正文语种 eng
  • 中图分类
  • 关键词

  • 入库时间 2022-08-18 00:16:05

相似文献

  • 外文文献
  • 中文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号