A NEW MATERIAL FOR GROUTING OF JOINTS WITH SMALL OPENINGS IN CONCRETE DAMS

机译:一种新的混凝土缝隙小缝接缝材料

获取原文
获取原文并翻译 | 示例
           

摘要

Successful experience with use of secondary monolithizing of dams by grouting of intercolumn joints is presented.rnGroutable joints in concrete dams. The 141-m-high and 759-m-long concrete gravity dam of the Bureya HPP consists of a powerhouse (P), spillway (S), and two dead-end sections - left (LB) and right (RB) bank sections (Fig. 1). Along its length, the dam is divided into 47 sections 15 and 24 m wide. During construction, sectioning of the spillway portion into columnar masses (columns) I-VII ranging in thickness from 14 to 17 m by temporary joints that were later grouted, was specified to ensure the dam's crack resistance when subjected to temperature effects. Grouting of the intercolumn joints should ensure the monolithic character of the dam and the transfer of compressive forces from the upstream to downstream columns [1].
机译:介绍了通过对立柱间缝进行灌浆来对坝进行二次整体浇铸的成功经验。 Bureya HPP的141米高和759米长的混凝土重力坝由动力厂房(P),溢洪道(S)和两个死角部分-左(LB)和右(RB)库段组成(图。1)。大坝沿其长度分为47个15和24 m宽的部分。在施工过程中,为了确保大坝在受到温度影响时的抗裂性,规定将溢洪道部分通过临时接缝分成厚度为14至17 m的圆柱状I-VII柱(块)。柱间缝的灌浆应确保坝体的整体性以及压缩力从上游柱到下游柱的传递[1]。

著录项

  • 来源
    《Power technology and engineering》 |2009年第6期|P.337-344|共8页
  • 作者单位

    JSC 'Spetsial'nyi Procktno-Izyskatcl'skii Institut 'Gidrospetsproekt,' Moscow, Russia;

    rnJSC 'Spetsial'nyi Procktno-Izyskatcl'skii Institut 'Gidrospetsproekt,' Moscow, Russia;

    rnJSC 'Spetsial'nyi Procktno-Izyskatcl'skii Institut 'Gidrospetsproekt,' Moscow, Russia;

    rnJSC 'Spetsial'nyi Procktno-Izyskatcl'skii Institut 'Gidrospetsproekt,' Moscow, Russia;

  • 收录信息
  • 原文格式 PDF
  • 正文语种 eng
  • 中图分类
  • 关键词

相似文献

  • 外文文献
  • 中文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号