首页> 外文期刊>Platts Electric Utility Week >MISO’s interim cost allocation plan approved;tough talks on permanent solution yet to come
【24h】

MISO’s interim cost allocation plan approved;tough talks on permanent solution yet to come

机译:MISO的中期成本分配计划获得批准;关于永久解决方案的激烈讨论尚未到来

获取原文
       

摘要

Tackling one of the “most difficult and contentious issues”nfacing the Midwest Independent Transmission System Operator, thenFederal Energy Regulatory Commission last week accepted a majornchange in the way the grid operator allocates the costs of networknupgrades for generation interconnection projects. Virtually all ofnthose costs will now fall on interconnection customers, with justn10% of the costs of larger upgrades being allocated system-wide.
机译:为了解决中西部独立输电系统运营商面临的“最困难和最具争议性的问题”,当时的联邦能源管理委员会上周接受了电网运营商为发电互连项目分配网络升级成本的方式的重大变化。现在,几乎所有这些成本都将落在互连客户身上,而大型升级成本中只有10%分配给了整个系统。

著录项

  • 来源
    《Platts Electric Utility Week》 |2009年第1102期|p.10-12|共3页
  • 作者

    Craig Cano;

  • 作者单位
  • 收录信息
  • 原文格式 PDF
  • 正文语种
  • 中图分类
  • 关键词

  • 入库时间 2022-08-18 01:27:05

相似文献

  • 外文文献
  • 中文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号