首页> 外文期刊>Pipeline & gas journal >Numerous Steps Required To Gain Permits For An LNG Terminal Expansion
【24h】

Numerous Steps Required To Gain Permits For An LNG Terminal Expansion

机译:获得LNG终端扩容所需的许多步骤

获取原文
获取原文并翻译 | 示例
       

摘要

It cannot be overemphasized that this article provides only a general overview of the extensive negotiations, research, and consultation involved in obtaining a joint EIS from FERC and its cooperating agencies. In addition to approval from the federal agencies in Table 1, the Elba III expansion project necessitated local permitting (such as county zoning permits) and multiple permits from the state of Georgia. The permitting efforts have been ongoing since 2005 and have encompassed hundreds of thousands of man hours, even though the project is an expansion of an existing facility.rnThe multi-tiered governmental approval process necessary to expand the Elba III Terminal Project typifies the efforts required in authorizing the construction and operation of an LNG terminal facility within the U.S. and its territories. However, the perception of natural gas as the bridge energy source of the near future, and the ever-increasing demand for natural gas, make the extensive permitting well worth the effort.
机译:不能过分强调本文仅概述了从FERC及其合作机构获得联合EIS所涉及的广泛的谈判,研究和咨询。除了表1中联邦机构的批准外,Elba III扩建项目还需要当地许可(例如县分区许可)和乔治亚州的多项许可。自2005年以来,许可工作一直在进行,尽管该项目是对现有设施的扩展,但仍涉及数十万工时。扩大Elba III航站楼项目所需的多层政府审批程序是该项目所需的努力。授权在美国及其领土内建设和运营LNG接收站。然而,人们将天然气视为不久的将来的桥梁能源,以及对天然气的需求不断增长,使得广泛的许可值得付出努力。

著录项

  • 来源
    《Pipeline & gas journal》 |2008年第10期|54565860|共4页
  • 作者单位
  • 收录信息 美国《科学引文索引》(SCI);美国《工程索引》(EI);美国《生物学医学文摘》(MEDLINE);美国《化学文摘》(CA);
  • 原文格式 PDF
  • 正文语种 eng
  • 中图分类
  • 关键词

  • 入库时间 2022-08-18 01:18:16

相似文献

  • 外文文献
  • 中文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号